Method of vibration and extrusion for cast-in-place concrete in pile hole and its vibration rod device
A technology of concrete and pouring into concrete, which is applied in sheet pile walls, processing of building materials, building structure, etc., can solve the problems of strong vibration, unsuitability, high noise, etc., and achieves low environmental impact, low energy loss, power small effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0017] Embodiment 1: Refer to Figure 1 for a schematic diagram of the construction of a single steel pipe force transmission member vibrator rod. It describes the method of vibrating and compacting the concrete in the pile hole of plain concrete piles when the pile diameter is small. The vibration source 1 is connected with the steel pipe 2 to form a vibration rod.
[0018] Referring to FIG. 2 , there is a vent hole 4 on the upper part of the steel pipe 2 , and a sealing partition 9 is welded on the upper edge of the vent hole 4 in the inner chamber of the steel pipe. The middle and upper part of the steel pipe 2 opens a material hole 5 . The diameter of the feed hole 5 is larger than that of the air hole 4 . The lower end of the steel pipe 2 is open.
[0019] Its technological process is:
[0020] 1. Drilling
[0021] 2. Pour concrete into the pile hole.
[0022] 3. Clean up the dregs at the orifice, and insert the orifice protection barrel 3 into the pile hole. Into t...
Embodiment 2
[0029] Embodiment 2: Figure 3 is a schematic diagram of the construction of a vibrating rod with a set of double steel pipe force transmission components. This method is adopted when the pile diameter is large, the pile length is long, and there is mud stagnant in the upper part of the cast-in-place concrete in the pile hole. Upper mud. The inner steel pipe 2 has the same structure as that shown in Fig. 1, and the lower end is open. The outer steel pipe 10 is open at the lower end and the upper end, the pipe wall is not perforated, and the lower end is provided with a temporary seal. Its construction process is:
[0030] 1. Drill holes in place.
[0031] 2. Lower the conduit and pour concrete underwater. Pull out the concrete pipe.
[0032] 3. Temporarily seal the lower part of the set of double-tube super-long vibrating rods. After inserting into the concrete, remove the temporary seal and keep vertical alignment. When the static sinking speed is slow, change it to vibra...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com