In situ cast-in-situ steel girder railway bridge deck pre-stress concrete channel beam construction method
A construction method and technology of trough beams, applied in the direction of bridges, bridge construction, erection/assembly of bridges, etc., to achieve the effect of easy quality control and safety, easy operation, and great promotion value
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0016] With reference to accompanying drawing 1,2, its processing step is divided into,
[0017] 1. After the erection and installation of the steel truss girder is completed, the in-situ cast-in-place bottom form platform 2 of the channel girder is assembled in the steel truss girder 1;
[0018] 2. Complete the channel beam construction template 15 installation, steel bar binding, concrete pouring and prestressing construction on the bottom formwork platform 2 to form the finished channel beam 8;
[0019] 3. Install the channel beam, lifting longitudinal beam 3, lifting longitudinal beam front outrigger 4, lifting longitudinal beam rear outrigger 5, lifting beam 6 and boom 7, lifting jack 9 and lifting joist 10, and make the channel beam Temporary cross braces 11, synchronously start eight lifting jacks 9 on the lifting beam 6, slowly lift the finished channel beam 8, and then slide the channel beam bottom mold platform 2 and the channel beam construction template 15 forward ...