Closed origin and arrival construction method of shield machine
A construction method and shield machine technology, applied in earthwork drilling, shaft lining, tunnel lining, etc., can solve the problems of large soil disturbance, increased construction cost, high site requirements, etc., and achieve the effect of reducing risks
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0032] A construction method for shielding confidential start and arrival, the method steps are as follows:
[0033] (1): Make plain concrete continuous wall close to the retaining structure of the continuous wall;
[0034] (2): Drill obliquely peripheral observation holes on the door to observe the stability and leakage of the soil;
[0035] (3): Cut off the concrete and steel bars on the door of the tunnel in sections, and replace the original continuous wall with plain concrete;
[0036] (4): Install shield machine receiving device and apply pre-force;
[0037] (5): Fill the steel sleeve of the receiving device to the required height;
[0038] (6): Conduct pressure test on steel sleeve;
[0039] (7): Shield machine tunneling construction until the shield tail of the shield machine enters or leaves the tunnel;
[0040] (8): Unload and disassemble the steel sleeve of the receiving device;
[0041] In order to facilitate a further understanding of the present invention, the presen...
PUM
Property | Measurement | Unit |
---|---|---|
Thickness | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com