Underground storey-adding process of frame structural building by one-by-one independent foundation underpinning method
A technology of independent foundation and frame structure, which can be used in underwater structures, building construction, infrastructure engineering, etc., and can solve problems such as structural instability.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0036] Embodiment 1: a kind of underground layer-adding process of the independent foundation of a frame structure building root-by-root underpinning method, which utilizes the top beams and top braces of the building to be built in the basement and the columns and foundations of the constructed basement to jointly support the upper structure, After completing the aforementioned techniques, continue to excavate the earthwork and carry out the construction of the columns and foundations of the remaining basement. The specific steps are:
[0037] (1) Construct all primary and secondary beams at the upper part of the foundation of the proposed basement, that is, at the indoor floor of the first floor of the existing building, and the primary and secondary beams are reliably connected to the upper frame column 1 of the existing building;
[0038] (2) The underpinning of the original independent foundation 2 is carried out one by one from the center to the surrounding or from the mi...
Embodiment 2
[0042] Embodiment 2: An underground layer-adding process of root-by-root underpinning method for the independent foundation of a frame structure building, which utilizes the top beam, top plate and top brace of the building to be built in the basement and the columns and foundations of the constructed basement to jointly support the upper part structure, continue to excavate the earth and carry out the construction of the columns and foundations of the remaining basement after completing the aforementioned techniques, the specific steps are:
[0043] (1) Construct all primary and secondary beams at the upper part of the foundation of the proposed basement, that is, at the indoor floor of the first floor of the existing building, and the primary and secondary beams are reliably connected to the upper frame column 1 of the existing building; The basement roof 5 is poured together during the primary and secondary beams of the ping, which can reduce the impact of the underground la...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com