Installation method for quickly removing and replacing middle-section furnace casing of large blast furnace

An installation method and technology in the middle section, applied in blast furnace, blast furnace details, blast furnace parts and other directions, can solve the problems of long construction period, high construction cost, heavy furnace shell weight, etc., to save material consumption, reduce construction cost, speed up The effect of construction progress

Active Publication Date: 2011-03-09
CHINA MCC 2 GRP CO LTD
View PDF4 Cites 12 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

In this replacement method, the lifted upper part 14 with the furnace shell is in an unstable state. During the jacking process, the local stability of each support point must be ensured to prevent the overall overturning of the furnace shell and endanger the safety of the construction personnel. Therefore, the entire construction The operation process is very dangerous; and because of the heav

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Installation method for quickly removing and replacing middle-section furnace casing of large blast furnace
  • Installation method for quickly removing and replacing middle-section furnace casing of large blast furnace
  • Installation method for quickly removing and replacing middle-section furnace casing of large blast furnace

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0012] see Figure 1 ~ Figure 3 Six sets of temporary support 1 are prefabricated before the shell of the middle section of the blast furnace is replaced, and each set includes the lower corbel 2, the support column 3 and the upper corbel 4. The upper corbel 4 is composed of a diagonal support 5 connected to the beam 7 through the connecting plate 6; the support column 3 is composed of a bracket 8, a base 9 and a column 10 connecting the bracket 8 and the base 9; The leg 2 is composed of a diagonal support 11 connected to a beam 13 through a connecting plate 12 . The upper corbel 4 is connected to the furnace shell 15 adjacent to the furnace shell part 14 to be replaced, the lower corbel 2 is connected to the furnace shell 16 adjacent to the next furnace shell part 14 to be replaced, and the supporting column 3 base 9 is connected to On the lower corbel 2 crossbeam 13, between the support column 3 bracket 8 and the upper corbel 4 crossbeam 7, reserve the height required for j...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to an installation method for quickly removing and replacing a middle-section furnace casing of a large blast furnace, belonging to the field of installation and construction of a metallurgical construction engineering metal structure. The invention provides a construction method for quickly removing and replacing the middle-section furnace casing after the installation of the entire blast furnace is finished, which comprises the following steps: dividing the furnace casing to be replaced into five sheets, manufacturing six temporary supports 1 before the replacement, and installing the six temporary supports 1 at three adjacent furnace casing sheets to be replaced (20, 21 and 22), wherein each furnace casing sheet to be replaced is provided two temporary supports 1; firstly replacing the first and the second furnace casing sheets (20 and 21), removing the two temporary supports 1 positioned at the first furnace casing sheet 20 after installation and fixation, and installing the two temporary supports 1 at a fourth furnace casing sheet 23 to be replaced, wherein the third and the fourth furnace casing sheets 22 and 23 are replaced simultaneously while the temporary supports are removed and installed; and replacing a fifth furnace casing sheet 24 without moving the temporary supports. The method does not destroy the overall stability of the structure, realizes the safe and reliable construction operation, has low material consumption for the temporary supports and ensures that the whole process can be finished in seven days, thereby achieving the effects of shortening the construction period and lowering the construction cost.

Description

[0001] Field [0002] The invention relates to an installation method for quickly dismantling and replacing a furnace shell in the middle section of a large-scale blast furnace, and belongs to the field of installation and construction of metal structures in metallurgical construction engineering. Background technique [0003] The manufacture and installation of large blast furnace shells is usually carried out by the factory in sections (or belts) and delivered to the construction site, and then assembled on site into one or more belts, and then installed from bottom to top. Because the steel plates used in the large-scale blast furnace shells are relatively thick and require high manufacturing techniques, it generally takes two months for each belt to be manufactured and transported to the site. Therefore, preliminary preparations for the production of the furnace shell must be carried out in advance. [0004] Xinjiang Bayi Steel Plant new 3# blast furnace (2500m 3 ) projec...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): C21B7/00
Inventor 韩露王明君周秀峰
Owner CHINA MCC 2 GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products