Reinforcing method for processing excessive deformation of primary support in tunnel construction
A technology for primary support and tunnel construction, applied in tunnels, tunnel linings, earthwork drilling and mining, etc., can solve problems such as time-consuming, labor-intensive and material-consuming, potential safety hazards, disturbance of tunnel surrounding rocks, etc., to improve durability, safety, good compactness
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0026] Such as figure 1 , figure 2 As shown, in the construction process of a certain tunnel, the support structure layer 1 of "sprayed concrete + steel arch frame" has been applied on the vault, but at the initial stage of construction, due to the excessive deformation of the support structure layer 1, and The deformation rate is too large, so the reinforcement method of the present invention will be used to deal with the excessive deformation of the initial support of the tunnel construction. The reinforcement method specifically includes the following steps:
[0027] (1) Adding steel arches: When the deformation of the support structure layer 1 is too large at the initial stage of tunnel construction, two layers of steel arch concrete structure layers are added outside the support structure layer 1 (that is, the first layer of steel arch concrete structure Layer 21 and the second layer of steel arch concrete structure layer 22), so that the steel arch concrete structure l...