Construction method of underground diaphragm wall
An underground diaphragm wall and construction method technology, applied in artificial islands, sheet pile walls, water conservancy projects, etc., can solve problems such as enlarged joints, safety risks of foundation pits, hidden dangers of durability, etc., to prevent water seepage and improve anti-seepage. Ability, the effect of prolonging the curing time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0016] A kind of construction method of underground continuous wall of the present invention, this method comprises the following steps: (1) excavate the trench of 6m long, 0.6m wide, 20m deep at predetermined position, place reinforcement cage, cast initial setting and final setting Concrete with a long time forms the underground connecting wall section; (2) Excavate trenches at adjacent positions of the formed underground connecting wall section, place steel cages, and pour ordinary concrete to form the underground connecting wall section. A distance of 0.5 meters is reserved between the underground connecting wall sections to ensure that the joints can be effectively lapped; (3) After the pouring of the two underground continuous wall sections is completed, when the concrete has not yet reached condensation, a diameter of 0.8 m is used at the joint of the two wall panels. A rotary pile excavator with a sleeve of 1.5 meters is used to form a hole, and concrete is poured into ...
Embodiment 2
[0018] A kind of construction method of underground continuous wall of the present invention, this method comprises the following steps: (1) excavate the trench of 6m long, 0.8m wide, 25m deep at predetermined position, place reinforcement cage, cast initial setting and final setting Concrete with a long time forms the underground connecting wall section; (2) Excavate trenches adjacent to the formed underground connecting wall section, place steel cages, and pour concrete with long initial setting and final setting times to form the underground connecting wall section, a 0.6-meter interval is reserved between two adjacent underground connecting wall sections to ensure that the joints can be effectively lapped; (3) After the pouring of the two underground A 1.0-meter-diameter rotary pile machine with a sleeve is used to form a hole at the wall joint, and a steel cage is placed in the hole, and then concrete is poured to form a rigid joint with a certain bearing capacity, so that...
Embodiment 3
[0020] A kind of construction method of underground continuous wall of the present invention, this method comprises the following steps: (1) excavate the trench of 6m long, 1m wide, 25m deep at predetermined position, place reinforcement cage, cast initial setting and final setting time The longer concrete forms the underground connecting wall section; (2) Excavate trenches at adjacent positions of the formed underground connecting wall section, place steel cages, and pour concrete with longer initial setting and final setting times to form the underground connecting wall section , a distance of 0.8 meters is reserved between two adjacent underground connecting wall sections to ensure that the joints can be effectively lapped; (3) After the pouring of the two underground A 1.2-meter-diameter rotary pile machine with a sleeve is used to form a hole at the joint of the width, and a steel cage is placed in the hole, and then concrete is poured to form a rigid joint with a certain ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com