Preloading structural part for high and large formwork support system

A support system, stacking preloading technology, applied in the connection of formwork/formwork/work frame, formwork/formwork/work frame, on-site preparation of building components, etc., can solve the inaccurate control of preloading data , the collapse of the formwork support system, the extension of the construction period and other problems, to achieve the effect of speeding up the preloading work efficiency, large unit area load, and reducing the lifting workload

Active Publication Date: 2013-12-11
THE 4TH CONSTR ENG CO LTD OF CHINA RAILWAY NO 4 ENG GRP
View PDF5 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Manual filling, lifting, loading and unloading of hundreds of tons of sandbags is required, the labor intensity is high, and the load value must be strictly controlled, which consumes a lot of machinery and manpower;
[0005] 2. Prolong the construction period
The affected construction period is 7 days or even longer;
[0006] 3. The control of preloading data is inaccurate, and overloading is likely to occur in rainy days, resulting in the collapse of the formwork support system of cast-in-place beams and slabs
The weight of the preloaded load with sandbags cannot be precisely controlled, especially in case of construction in rainy days, the rainwater poured into the sandbags will cause the accumulation of preloaded load to increase, and in severe cases, the support system will easily collapse and cause major safety accidents;
[0007] 4. The stacking height is too high to ensure the stability of the stacking carrier
Since the specific gravity of reinforced concrete is about 2.5 tons / m 3 , while the specific gravity of the sandbag is 1.6 tons / m 3 , and the preload generally needs to be overloaded by 1.2 times the preload. If the height of the beam section is 3.0m, then the height of the piled sand bag should reach: 3.0*(2.5 / 1.6)*1.2=5.625m, so close to the 6m high Sandbags are difficult to ensure the safety and stability of the accumulation body, and protective measures need to be taken to increase safety risks and investment;
[0008] 5. Using prefabricated concrete blocks as the load, lifting the prefabricated concrete blocks by crane to the upper part of the formwork support system for preloading can solve the above problems, but it is difficult to obtain materials for the prefabricated concrete blocks, and the transportation cost increases. If the precast concrete blocks are poured on site will be wasted again

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Preloading structural part for high and large formwork support system
  • Preloading structural part for high and large formwork support system
  • Preloading structural part for high and large formwork support system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0029] see figure 1 , used for the stacked preloaded structural parts of the tall formwork support system, including brick pier components and preloaded load components;

[0030] The brick pier assembly is composed of a first brick pier block 11 and a second brick pier block 12; wherein, the first brick pier block 11 is a rectangular column with a length of 1 meter, a width of 1 meter, and a height of 1.2 meters. The top of pier block 11 is provided with first smoothing layer 13; Smoothing layer 14; the top surface of the first smoothing layer 13 is horizontal to the top surface of the second smoothing layer 14; the center of the first brick pier 11 and the center of the second brick pier 12 are 4.5 meters apart;

[0031] The preloaded load components are composed of preloaded load units, and the preloaded load components are composed of 2 to 10 preloaded load units arranged horizontally;

[0032] The preloaded load unit is approximately a rectangular block, and is composed...

Embodiment 2

[0036] see Figure 4 , used for the stacked preloaded structural parts of the tall formwork support system, including brick pier components and preloaded load components;

[0037] The brick pier assembly is composed of a first brick pier block 11 and a second brick pier block 12; wherein, the first brick pier block 11 is a rectangular column with a length of 1 meter, a width of 1 meter, and a height of 1.5 meters. The top of pier block 11 is provided with the first plastering layer 13; Smoothing layer 14; the top surface of the first smoothing layer 13 is horizontal to the top surface of the second smoothing layer 14; the center of the first brick pier 11 and the center of the second brick pier 12 are 4.5 meters apart;

[0038] The preloaded load components are composed of preloaded load units, and the preloaded load components are composed of six preloaded load units arranged horizontally;

[0039]The preloaded load unit is approximately a rectangular block, and is composed...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a preloading structural part for a high and large formwork support system, which is used for solving the technical problems caused by preloading detection using sandbags or concrete blocks. The preloading structural part comprises a brick pier component and preloading components, wherein the brick pier component consists of a first brick pier block and a second brick pier block; a first floating layer is arranged at the top of the first brick pier block; a second floating layer is arranged at the top of the second brick pier block; the top surface of the first floating layer is level with the top surface of the second floating layer; each preloading component consists of 2-10 preloading units in horizontal arrangement; the preloading components are piled at the top of the brick pier component layer by layer; and 2-20 layers of preloading components are paved at the top of the brick pier component. The preloading structural part provided by the invention has the beneficial effects that a relatively large unit area load can be obtained under the condition of relatively low loading height so as to reduce the height of a preloading body and the hoisting workload of the preloading body and guarantee high safety.

Description

technical field [0001] The invention belongs to the field of building construction, and in particular relates to a surcharged preloaded structural member used for a tall formwork support system. Background technique [0002] With the continuous development of social economy, architectural design is constantly developing towards large span and large space, and the design and application of cast-in-situ beams and slabs with super large cross-section and super long span are becoming more and more frequent. For the formwork support system of reinforced concrete beams and slabs with large cross-sections during construction, in order to verify the strength, stiffness and stability of the formwork support system and eliminate the adverse effects of elastic and plastic deformation of the support system and foundation, it is often necessary to pour concrete The formwork support system of the reinforced concrete beam slab is preloaded and preloaded to ensure the safety and stability o...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E04G17/00E04G11/48E04G13/04E04G25/00
Inventor 李明董燕囡施通来席丽君胡强
Owner THE 4TH CONSTR ENG CO LTD OF CHINA RAILWAY NO 4 ENG GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products