Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Underground and overground continuous construction method for major-diameter high flat bed pile in sandy soil stratum

A high-capped pile and construction method technology, applied in the field of building foundation engineering, can solve problems such as the instability of the casing, the existence of safety hazards, and uneven stress distribution, and achieve the goals of reasonable design of construction steps, easy pile quality, and expanded adaptability Effect

Active Publication Date: 2014-01-29
WUHAN SURVEYING GEOTECHN RES INST OF MCC
View PDF6 Cites 8 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

First of all, in the first construction method, there will be a weak structural surface at the pile connection site. Small strain detection usually shows a "broken pile" waveform here, which poses a safety hazard. When the pile body bears a large load, the stress distribution is uneven and easy Stress concentration occurs, which may lead to broken piles or structural damage in severe cases
Secondly, the second method is to pull up the casing below the ground and use it as a steel formwork for the pile body above the ground. It is feasible, but because the casing cannot be cleaned and painted with release paint, and it is difficult to control the verticality of the casing, There are problems such as rough surface of the pile body above the ground level, pockmarked surface, inclined pile body on the ground, and instability of the casing
Finally, the third method, since the casing needs to be pulled out inside the steel formwork, it is necessary to reserve enough space for the casing to be pulled up, and the diameter of the upper pile body will eventually be much larger than that of the lower pile body, but for petrochemical LNG For engineering projects, because the design has very strict requirements on the pile diameter, the diameter of the upper pile body can neither exceed the design diameter by 50mm nor be lower than the design pile diameter, which is generally not applicable

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Underground and overground continuous construction method for major-diameter high flat bed pile in sandy soil stratum
  • Underground and overground continuous construction method for major-diameter high flat bed pile in sandy soil stratum
  • Underground and overground continuous construction method for major-diameter high flat bed pile in sandy soil stratum

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0026] according to Figure 1 to Figure 6 Shown:

[0027] A method for continuous construction on large-diameter high-capped piles in sandy soil stratum, comprising the following steps:

[0028] Ⅰ) Use a rotary drilling rig to dig a hole at a predetermined position, bury a 3m-10m steel casing 4 according to the stratum conditions, drill to the designed hole depth, clear the hole, and form a drill hole 1, and place a reinforcement cage 2 through the pre-construction platform 3 and The grouting conduit 52, after the secondary hole clearing, begins to pour the underwater concrete, and suspends the pouring until it is about 50cm-100cm below the ground level;

[0029] Ⅱ) Remove the upper pre-construction platform 3 and the grouting conduit 52, slowly pull up the steel casing 4, so that the top of the steel casing 4 is 60cm-100cm above the ground, and continue pouring with the grouting pump or the rubber hose 53 at the end of the grouting funnel 51 For underwater concrete, stop pou...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

An underground and overground continuous construction method for a major-diameter high flat bed pile in a sandy soil stratum comprises the following steps: (I) a hole is drilled and cleaned, steel reinforcement cages and a grouting guide pipe are placed, and underwater concrete is poured; (II) an upper earlier stage construction platform and the grouting guide pipe are removed, a pile casing is pulled upwards slowly, and pouring is suspended when the concrete pouring height is 30-50cm above the ground; (III) the pile casing is pulled out slowly, and a grouting funnel is removed; (IV) concrete 5m below an orifice is vibrated, remaining concrete and slurry around the drilled hole are cleaned up, and sand and sand bags are piled up at the bottom of a steel formwork in a filling mode; (V) overground concrete is poured and vibrated repeatedly through a vibrating spear, and pouring of the overground concrete is stopped when the surface of the overground concrete exceeds a certain height; (VI) secondary vibrating is conducted within 30 minutes before initial setting of the overground concrete; form stripping is conducted 24 hours later, and maintenance is conducted. According to the underground and overground continuous construction method for the major-diameter high flat bed pile in the sandy soil stratum, the construction steps are reasonable in design, construction is convenient, cost is low, the construction period is short, and construction quality is controllable; the high flat bed pile after construction has the advantages that the connection position continuity of a pile body is good, so that the pile body is free of leakage, and pile quality is high.

Description

technical field [0001] The invention relates to the technical field of building foundation engineering, in particular to an underground continuous construction method for large-diameter and high-capped piles in sandy soil stratum. Background technique [0002] At present, our country is in a period of rapid development of engineering construction. The use of advanced design and construction technology to achieve the construction goals of saving investment, shortening the construction period, and ensuring safety has always been pursued by the engineering community. Bored pile foundations are currently widely used at home and abroad. A form of deep foundation, generally low-capped piles, which can meet the needs of the project according to the normal construction technology, but for some foreign-related petrochemical engineering LNG projects, it is gradually required to use large-diameter high-capped piles, currently for high-capped piles There are mainly the following three c...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E02D5/40E02D5/66
Inventor 杨昌斌李晓柱陈文俊沈新中路文辉管海啸黄浩
Owner WUHAN SURVEYING GEOTECHN RES INST OF MCC
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products