Installation method for anti-sedimentation well cover
An anti-subsidence and manhole cover technology, applied in the field of municipal engineering, can solve problems such as affecting urban road traffic safety and service level, restricting the quality of urban road engineering, affecting road smoothness and aesthetics, etc., achieving high strength, easy promotion and application, equipment less demanding effects
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0026] When the periphery of the old manhole cover is slightly damaged and the foundation is good, a method for replacing the anti-settling manhole cover includes the following steps:
[0027] a. Take out the old manhole cover;
[0028] b. Take the old manhole cover as the center, directly set out the line according to the 1.0m, cut and remove the periphery of the inspection well to the standard width, and control the depth at 12~15cm;
[0029] c. Clean the surface of the base of the manhole cover, calculate the volume to be filled, estimate the amount of epoxy asphalt mixture, and then use liquid epoxy asphalt: AC10 grade ingredients (material is limestone) as 1: (5~6) in the vertical Fully mix the two in a forced mixer for 1 to 3 minutes for use, and finally use part of the epoxy asphalt mixture to level the base of the manhole cover;
[0030] d. Place the manhole cover adjustment ring;
[0031] e. Install the leak-proof pot;
[0032] F. Fill the well-mixed epoxy asphalt ...
Embodiment 2
[0038] When there is serious damage around the old manhole cover and the base is not good, a method for replacing the anti-settling manhole cover includes the following steps:
[0039] a. Take out the old manhole cover;
[0040] b. Take the old manhole cover as the center, set out the line according to the actual damaged range, cut and remove the periphery of the inspection well to the standard width, and excavate the depth according to the actual situation. If the depth exceeds 15cm, cement brick masonry should be used to ensure that the depth is 12~15cm;
[0041] c. Clean the surface of the base of the manhole cover, calculate the volume to be filled, estimate the amount of epoxy asphalt mixture, and then use liquid epoxy asphalt: AC13 grade ingredients (basalt) as 1: (5~6) in the vertical Fully mix the two in a forced mixer for 1 to 3 minutes for use, and finally use part of the epoxy asphalt mixture to level the base of the manhole cover;
[0042] d. Place the manhole co...