Construction method for concrete diaphragm wall cofferdam heightening
A concrete anti-seepage wall and construction method technology, applied in the direction of basic structure engineering, construction, etc., can solve problems such as the need for repair of cofferdam body sections, achieve the effect of reducing the requirements of construction conditions and high processing efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment
[0022] The cofferdam at the outlet of the diversion tunnel on the left bank of a hydropower station was originally treated with a concrete anti-seepage wall. After considering the construction period requirements of the overflow node, the height of the weir top of the cofferdam during the dry season of the outlet was designed to be heightened and adjusted by geomembrane anti-seepage treatment. During the flood season, due to the surge in flow, the side of the cofferdam near the river suffered settlement and deformation. In order to ensure the overall stability of the cofferdam and avoid further expansion of the damage to the cofferdam, the broken weir was filled with hydraulic pressure. After the cofferdam body was broken and filled with water, part of the cofferdam body section was damaged. The maximum gap width was about 50m, and the maximum depth was about 16m. Secondary cofferdam filling and anti-seepage treatment were required. After researching and comparing plans from t...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com