Installation method of double platform elevator without scaffolding
A technology without scaffolding and installation method, used in elevators, transportation and packaging in buildings, lifting equipment in mines, etc. The effect of construction period, saving of erection and dismantling costs, and reduction of operating time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0035] Such as Figure 1-3 As shown, a double-platform scaffold-free elevator installation method is characterized in that the installation procedure is: making samples and setting out wires—installation of machine room equipment—temporary platform erection—bottom pit equipment installation—car platform assembly— Installation of moving down platform—installation of traction type and speed limiter—slow train debugging—use of platform construction—removal of platform and installation of counterweight—car hardcover—fast train commissioning, details are as follows:
[0036] Make the model and set out the wire: make the model frame according to the actual relevant dimensions of the elevator car, counterweight, guide rail and other components, install the model frame in the machine room, then hang the plumb line according to the model frame, and stabilize the plumb line;
[0037] Machine room equipment installation: install traction machine, speed limiter and control cabinet in the ...
Embodiment 2
[0049] A project includes the installation of 4 high-speed elevators, the length of the elevator shaft is 70m, and the maximum operating speed of the elevator is 6m / s. The contract elevator construction period for elevator installation is 60 days. Since the construction progress of the civil works is 18 days later than planned, the actual construction period of the elevator is only 42 days. The traditional scaffolding elevator installation method has been unable to complete the elevator installation task within the specified construction period. Therefore, The technicians conducted several studies and discussions on the plan, and formulated a double-platform elevator installation method:
[0050] The elevator installation procedure used is: making prototypes and laying out wires—machine room equipment installation—temporary platform erection—pit equipment installation—car platform assembly—downward platform installation—traction and speed governor installation ——Slow train debug...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 