The construction method of hoisting the stiffening beam of suspension bridge with cross-cable crane walking with beam

A construction method and crane technology, which is applied to bridges, bridge construction, erection/assembly of bridges, etc., can solve the problems of increasing equipment investment, site occupation and labor costs, low efficiency of swinging construction, and limited scope of use, etc., to achieve economical Significant benefits and social benefits, reduced construction procedures and procedures, saving space and labor

Active Publication Date: 2017-04-12
CCCC FOURTH HIGHWAY ENG +1
View PDF10 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, the swing method can only transport the stiffened beams for a short distance, the scope of use is limited, and the construction efficiency of the swing is low
[0003] In the prior art, there is also a method of installing stiffening beams by walking with a beam across a cable crane, such as Chinese patent application No. 200910113846.5, titled "A Method for Erecting the Main Girder of a Suspension Bridge Using a Double-machine Double-Hanger Hydraulic Numerical Controlled Cable Crossing Crane" Invention patent, which uses two cross-cable cranes as a group to jointly lift a section of stiffened beam, but it can only realize walking with the beam at the gentle place of the suspension cable, and two cranes are needed at the part with a large inclination angle of the suspension cable The stiffening beam is transported between machines by swinging, which is less efficient
Moreover, this method has complex procedures, requires a lot of equipment, and is costly, and because the beam section cannot pass through the hoisted beam section when walking with the beam, it is necessary to set up beam yards on both sides of the bridge, and install a set of cranes at the cable towers on both banks. , increasing equipment investment, site occupancy and labor costs

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • The construction method of hoisting the stiffening beam of suspension bridge with cross-cable crane walking with beam
  • The construction method of hoisting the stiffening beam of suspension bridge with cross-cable crane walking with beam
  • The construction method of hoisting the stiffening beam of suspension bridge with cross-cable crane walking with beam

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0044] figure 1 It is a method flowchart of the present invention, mainly comprising the following steps:

[0045] (1) Beam section prefabrication: Set up a beam field on one side of the bridge, prefabricate the suspension bridge section, and make the width of each beam section in the transverse bridge direction greater than its length along the bridge direction when prefabricating;

[0046] (2) Preset cable-stayed beams: During the construction of the tower column, the pre-stressed pipes are pre-buried in the tower body in advance, and the prestressed cable-stayed beams are set; the cable-stayed beams are used for fixed lifting;

[0047] (3) Set up the cross-cable crane and anti-tension system: install the cross-cable crane on the side cables of the mid-span of the tower column on the bank of the beam yard, and set up the anti-tension system on the side-span side approach bridges of the tower columns on both banks;

[0048] (4) Installation of the beam span section on the ba...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a construction method for hoisting a stiffening girder of a suspension bridge by adopting girdle-carrying traveling of a deck erection gantry. Firstly, a side span girder segment is mounted through cooperation of reverse pulling systems and the deck erection gantry, is fixed by a prearranged prestress cable-stayed beam and is taken as a hoisting platform for hoisting of other girder segments; a girder field is arranged on one bank, hoisting of all the girder segments is realized through girdle-carrying traveling of the single deck erection gantry, little equipment investment is consumed, the process is simple, the construction efficiency is high, and the cost is low.

Description

technical field [0001] The invention relates to the field of hoisting and construction of stiffening beams of suspension bridges, in particular to a construction method for hoisting and hoisting stiffening beams of suspension bridges by using a cross-cable crane. Background technique [0002] During the construction of the stiffened girder of the suspension bridge, the cross-cable crane is often used for hoisting construction. A cross-cable crane is more suitable for vertical lifting operations. Generally, the stiffening beam to be hoisted is transported to the bottom of the lifting point of the cross-cable crane by a ship, and the cross-cable crane lifts it to an appropriate height through a sling to connect with the sling. However, when the shoal or mountainous area is unnavigable, the stiffened beam can only be transported to one point, and the stiffened beam can be moved to the designed installation position by swinging or erecting a bracket. For example, the name of Chi...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): E01D21/00
CPCE01D21/00
Inventor 林新元孙存良王志强孟祥源钱育强宋大成李正军单晓东吴琼明侯建平杨浩马利刚孙凯刘帅帅庞庆冯雄飞王栋蔡悬
Owner CCCC FOURTH HIGHWAY ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products