Load emergency adjusting method and load emergency adjusting device for thermal power generator unit in AGC manner
A technology for thermal power units and adjustment methods, which is applied in adaptive control, control/regulation systems, instruments, etc., can solve problems such as large drop rate and power grid frequency drop, and achieve the effects of low cost, improved stability, and good reliability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0039] Such as image 3 As shown, a thermal power unit load emergency flexible and fast adjustment device under grid failure, including an analog signal collector, a switch signal collector, a multiplier MUL, an RS trigger, a function generator, a logic OR module, a logic NOT module, High and low limit alarm module and analog switcher, in which:
[0040] The digital signal collector DI receives the power grid failure unit emergency mode switching / deactivation signal issued by the power grid, sends one way to the setting terminal S of the RS flip-flop, and one way is sent to the logic or module after being reversed by the logic NOT module An input terminal X1 of OR, the main steam pressure deviation value signal obtained by calculating the difference between the main steam pressure set value and the main steam pressure measurement value of the analog signal collector S receiver group is sent to the high and low limit alarm module HLALM The other input terminal X2 of the logica...
Embodiment 2
[0047] An emergency load adjustment method for thermal power units in the AGC mode. When a power gap accident occurs in the power grid, it is judged whether the regional control deviation value exceeds the first setting range and whether the main steam pressure deviation value exceeds the second setting range:
[0048] (1) If the unit regional control deviation value exceeds the first setting range and the main steam pressure deviation value does not exceed the second setting range, artificially accelerate the load adjustment;
[0049] (2) If the regional control deviation value of the unit does not exceed the first setting range, automatic load adjustment is performed;
[0050] (3) If the regional control deviation value of the unit exceeds the first setting range and the main steam pressure deviation value exceeds the second setting range, automatic load adjustment will be performed.
[0051] When the power grid fails, such as large-scale power gap accidents such as UHV DC u...
Embodiment 3
[0056] Taking Shandong Power Grid in North China as an example, its frequency regulation and peak regulation are in accordance with the "Implementation Rules for Grid-connected Operation Management of Power Plants in North China Region". %; the general thermal power unit with intermediate storage bin pulverizing system is 2% of the rated active power of the unit. Taking a 300MW direct-blowing drum boiler unit in Shandong Power Network as an example, according to regulations, its regulation rate is 300×1.5%=4.5MW / min, that is, the standard regulation rate set in analog generator A1 is 4.5, which is also It is the load adjustment rate of the unit during normal AGC adjustment. The upper limit H of the high and low limit alarm module HLALM is set to 0.6 and the lower limit L is set to -0.6. After the field performance test of the unit, when the load adjustment rate is not greater than 8MW / min, the main parameters such as the main steam pressure can be controlled within the specif...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com