Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Novel steel pipe pile bed rock drilling anchoring method

A technology for steel pipe piles and drilled anchors, which is applied in the direction of sheet pile walls, foundation structure engineering, construction, etc., can solve problems such as inability to meet anti-scouring requirements, insufficient driving depth of steel pipe piles, and increase cross-operation procedures, etc., to achieve The effect of fast construction speed, small size, and convenient entry and exit

Inactive Publication Date: 2017-11-24
CHINA RAILWAY SIXTH GRP CO LTD +1
View PDF4 Cites 8 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] When a railway or highway bridge crosses a waterway or a port, it is necessary to build trestle bridges and water work platforms and other wading structures in shoals with thin covering layers or even no covering layers or shallow waters with pebbles under the riverbed. Most of the buildings use various types of steel pipe piles as the foundation, and the steel pipe piles cannot be driven into the bedrock below the overburden layer. During construction, it is often encountered that the steel pipe piles are not driven deep enough to meet the anti-scouring requirements. At this time, the steel pipe pile needs to be anchored at the bottom of the pile. In most cases, the pile bottom anchoring operation needs to be punched with a percussion drill, and then the steel pipe pile is driven into the pile and concrete is poured into the pile.
However, the problems existing in the method of "percussion drilling, punching and anchoring" are as follows: 1) It is necessary to use a percussion drilling rig, which increases the investment in mechanical equipment, and the drilling rig needs to repeatedly enter and exit the working face, which increases the cross-operation process and increases the safety risk; 2) it must be erected There are high safety risks during impact construction, most of which are high-altitude operations, which require precise alignment and difficult construction; 3) Only one hole position can be impacted at a time, and the next one can be constructed after completion The hole position takes a long time, and the rest of the construction process needs to wait during the impact construction

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Novel steel pipe pile bed rock drilling anchoring method
  • Novel steel pipe pile bed rock drilling anchoring method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0012] A novel steel pipe pile foundation rock drilling and anchoring method, comprising the following steps: first construct a trestle bridge or a platform near the thicker part of the river bed covering layer on the bank, lay the bridge deck, and form an operation platform; use the operation platform to lower the Φ630mm steel pipe, first The lowered Φ630mm steel pipe forms the working space. Use the construction casing to drill the anchor hole 2 on the bedrock 1 directly below the steel pipe. After drilling the anchor hole, lower the anchor bar 3 and consolidate it with grouting, and then backfill the broken pieces in the Φ630mm steel pipe. Stone or concrete 4 to form an anchoring body in which the anchoring steel bar and the steel pipe work together to achieve a stable effect.

[0013] Temporary structures such as trestles and platforms have met the bearing capacity requirements during construction, and other structures can continue to be erected while anchoring steel pipe p...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to the field of steel pipe pile anchoring, in particular to a novel steel pipe pile bed rock drilling anchoring method. The novel steel pipe pile bed rock drilling anchoring method comprises the following steps that a trestle or platform close to the thick part of a shoreside riverbed covering layer is constructed first, bridge deck slabs are laid, and an operation platform is formed; a steel pipe is placed downwards through the operation platform, an operation space is formed by the steel pipe placed downwards first, anchor rod holes are drilled in bed rock under the steel pipe through a construction casing pipe drill, anchor steel bars are placed downwards after the anchor rod holes are drilled, grouting consolidation is conducted, the steel pipe is backfilled with macadam or concrete to form an anchoring body achieving the combined effect of the anchor steel bars and the steel pipe, and then a stabilizing effect is achieved. According to novel steel pipe pile bed rock drilling anchoring method, anchoring operation can be conducted through multiple drilling machines simultaneously, the construction progress is guaranteed, input is low, little load is added to a temporary power utilization line, and the line does not need to be specially arranged.

Description

technical field [0001] The invention relates to the field of steel pipe pile anchorage, in particular to a novel steel pipe pile bedrock drilling and anchorage method. Background technique [0002] When a railway or highway bridge crosses a waterway or a port, it is necessary to build trestle bridges and water work platforms and other wading structures in shoals with thin covering layers or even no covering layers or shallow waters with pebbles under the riverbed. Most of the buildings use various types of steel pipe piles as the foundation, and the steel pipe piles cannot be driven into the bedrock below the overburden layer. During construction, it is often encountered that the steel pipe piles are not driven deep enough to meet the anti-scouring requirements. At this time, the steel pipe pile needs to be anchored at the bottom of the pile. In most cases, the pile bottom anchorage needs to be punched with a percussion drill, and then the steel pipe pile is driven into the ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D7/00E02D5/74E02D27/52
CPCE02D7/00E02D5/74E02D27/525
Inventor 刘志勇岳海飞袁志富金路胡为谷金明
Owner CHINA RAILWAY SIXTH GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products