Construction method of urban comprehensive pipe gallery
A technology of integrated pipe gallery and construction method, applied in artificial islands, water conservancy projects, infrastructure projects, etc., can solve problems such as unreasonable utilization of construction space, and achieve the effects of improving construction efficiency, strengthening structural strength, and high utilization rate
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0030] A construction method for an urban comprehensive pipe gallery, such as figure 1 and figure 2 shown, including the following steps:
[0031] Step 1, put two rows of steel sheet piles 5 below the ground;
[0032] Step 2, inserting two rows of prefabricated ground walls 1 into the soil between the two rows of steel sheet piles 5, and making the prefabricated ground walls 1 stand opposite each other;
[0033] Step 3, inject cement slurry into the soil below the ground between the two prefabricated ground walls 1, and mix the cement slurry with the soil to form cement soil 2;
[0034] Step 4: Excavate the soil between the two prefabricated ground walls 1 to the upper surface of the prefabricated ground wall 1, and then set a second support body between the two steel sheet piles 5 for fixing the two steel sheet piles 5 s position;
[0035] Step 5, continue to dig down until the upper surface of the cement soil 2 is dug, and connect the first support body at the top of th...
Embodiment 2
[0048] A construction method for an urban comprehensive pipe gallery, such as image 3 shown, including the following steps:
[0049] Step 1, put two steel sheet piles 5 and the prefabricated ground wall 1 sequentially below the ground, the steel sheet piles 5 are distributed on both sides of the prefabricated ground wall 1, wherein the top of the prefabricated ground wall 1 is lower than the ground, and the top of the steel sheet pile 5 is flush with the ground Flat, the bottom end is lower than the top of the prefabricated ground wall 1;
[0050] Step 2, inject cement slurry under the soil between the prefabricated ground walls 1, and mix the cement slurry with the soil to form cement soil 2;
[0051] Step 3: Excavate the soil between the prefabricated ground walls 1, and during the excavation process, first set a second support body between the two rows of opposing steel sheet piles 5 for supporting the two rows of opposing steel sheet piles 5, until the top of the prefabri...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More - R&D
- Intellectual Property
- Life Sciences
- Materials
- Tech Scout
- Unparalleled Data Quality
- Higher Quality Content
- 60% Fewer Hallucinations
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2025 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com