Construction method of new structure of crtsⅢ slab ballastless track in tunnel section
A technology of slab-type ballastless track and new structure, which is applied in the direction of track, track laying, track maintenance, etc., can solve the problems of numerous slab track construction procedures, long working procedures, and complicated technology, so as to optimize the construction process, reduce the project cost, improve the The effect of construction speed
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0024] see Figure 1-3 , the present invention provides a technical solution: a construction method for a new structure of CRTSⅢ slab ballastless track in the tunnel section, the method includes the following steps:
[0025] a Supporting layer and base construction: During the base construction, the supporting layer is poured continuously longitudinally along the line, and a transverse pre-crack is set every 5m. The width of the slit is about 1mm and the depth is 80mm. The supporting layer of C20 plain concrete is set and the laying of steel bars is cancelled. ;
[0026] b Laying of steel mesh: When laying steel mesh, the steel bar under the door-shaped steel bar of the track plate is located under the door-shaped steel bar, and does not pass through the door-shaped steel bar. A protective layer pad is placed under the steel mesh sheet, and the protective layer pad is placed per square meter. There are at least 4 spacers in the meter;
[0027] c Transverse belt construction:...
Embodiment 2
[0032] see Figure 1-3 , the present invention provides a technical solution: a construction method for a new structure of CRTSⅢ slab ballastless track in the tunnel section, the method includes the following steps:
[0033] a Supporting layer and base construction: During the base construction, the supporting layer is continuously poured longitudinally along the line, and a transverse pre-crack is set every 5m. The width of the slit is about 1mm and the depth is 100mm. The supporting layer of C20 plain concrete is set, and the reinforcement laying is canceled ;
[0034] b Laying of steel mesh: When laying steel mesh, the steel bar under the door-shaped steel bar of the track plate is located under the door-shaped steel bar, and does not pass through the door-shaped steel bar. A protective layer pad is placed under the steel mesh sheet, and the protective layer pad is placed per square meter. There are at least 4 spacers in the meter;
[0035] c Transverse belt construction:...
Embodiment 3
[0040] see Figure 1-3 , the present invention provides a technical solution: a construction method for a new structure of CRTSⅢ slab ballastless track in the tunnel section, the method includes the following steps:
[0041] a Supporting layer and base construction: During the base construction, the supporting layer is poured continuously along the line longitudinally, and a transverse pre-crack is set every 5m. The width of the slit is about 1mm and the depth is 90mm. The supporting layer of C20 plain concrete is set, and the laying of steel bars is canceled ;
[0042] b Laying of steel mesh: When laying steel mesh, the steel bar under the door-shaped steel bar of the track plate is located under the door-shaped steel bar, and does not pass through the door-shaped steel bar. A protective layer pad is placed under the steel mesh sheet, and the protective layer pad is placed per square meter. There are at least 4 spacers in the meter;
[0043] c Transverse belt construction: Du...