A construction method for the Bailey frame platform of the transfer floor of a high-rise building
A technology for high-rise buildings and construction methods, which is applied in the construction, building structure, and building materials processing. Ideal body, stable and reliable platform
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0028] The conversion layer of the high-rise building in this embodiment is located above the nine floors, with a mezzanine on one side and no mezzanine on the other side. The construction method of the Bailey platform is shown in the figure, and the construction is carried out as follows:
[0029] The first step is to install the lattice column-such as figure 1 As shown, on both sides of the lattice column foundation 1-2, which is integrated with the building foundation 1-1, the positions below the beams of the corresponding conversion floor are installed with embedded anchor bolts 1-3 to install the lattice columns 1 distributed at intervals. The lattice column 1 of this embodiment adopts the standard tower sections 1-4 of the tower crane to be spliced section by section from bottom to top;
[0030] When splicing installation, use Figure 2.1 , Figure 2.2 , Figure 2.3 The tool-type operating platform 2 shown has a channel steel profile welded to form a "concave"-shaped tableto...
PUM
Login to View More Abstract
Description
Claims
Application Information