Construction method for forming pile in reinforced concrete structure or hard integral bedrock
A technology of reinforced concrete and construction methods, which is applied in basic structure engineering, sheet pile walls, buildings, etc., can solve the problem of hard rock hole formation difficult to be popularized, etc., achieve construction operations that avoid blasting and/or damage to structures, overcome quality Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0074] 1. Characteristics of construction method
[0075] 1.1 The rapid hole-forming method in reinforced concrete structure or hard monolithic bedrock effectively solves the problem of rapid hole-forming construction on reinforced concrete structures without blasting and without destroying the structure, thus ensuring the quality and safety requirements.
[0076] 1.2 Effectively solve the problem that the groundwater level is high, the water seepage in the hole is large, and the top surface elevation of the pile foundation is relatively shallow under the water. There is no need for drainage and anti-seepage treatment to form holes on reinforced concrete structures.
[0077] 1.3 It solves the problem of not using mud when forming holes, which effectively protects the balance of the ecological environment and saves the construction site.
[0078] 1.4 The method of rapid hole formation in reinforced concrete structure or hard monolithic bedrock is adopted. The requirements for ...