Construction method for demolition of low pier bridge
A construction method and technology for bridges, applied in bridges, bridge maintenance, bridge reinforcement, etc., can solve the problems of heavy lifting section weight, slow construction speed, less research, etc., to reduce construction cost, save construction period, and simple operation. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0029] A construction method for demolishing a bridge with low piers, comprising the following steps:
[0030] (1) Determine the order of bridge demolition: if the marked demolition objects are in different positions and have no connection with each other, directly use the crusher to dismantle them; and if the marked demolition objects are in the same position and are connected, follow the order of first light and then heavy, first high and then low Sequentially use the crusher for demolition; the driving oil pressure of the crusher is 160kg / cm 2 , The strike frequency is 200bpm, and there is a breaker with a drill rod diameter > 140mm;
[0031] (2) Ground protection: If the original ground or road under the bridge needs to be rebuilt, no ground protection measures shall be taken; if the road under the bridge needs to be used normally after the bridge is demolished, the road surface protection shall be carried out;
[0032] Pavement protection shall be in the form of filling ...
Embodiment 2
[0044] A construction method for demolishing a bridge with low piers, comprising the following steps:
[0045] (1) Determine the order of bridge demolition: if the marked demolition objects are in different positions and have no connection with each other, directly use the crusher to dismantle them; and if the marked demolition objects are in the same position and are connected, follow the order of first light and then heavy, first high and then low Sequentially use the crusher for demolition; the driving oil pressure of the crusher is 170kg / cm 2 , The strike frequency is 300bpm, and has a breaker with a drill rod diameter > 140mm;
[0046] (2) Ground protection: If the original ground or road under the bridge needs to be rebuilt, no ground protection measures shall be taken; if the road under the bridge needs to be used normally after the bridge is demolished, the road surface protection shall be carried out;
[0047] Pavement protection shall be in the form of filling soil ...
Embodiment 3
[0059] A construction method for demolishing a bridge with low piers, comprising the following steps:
[0060] (1) Determine the order of bridge demolition: if the marked demolition objects are in different positions and have no connection with each other, directly use the crusher to dismantle them; and if the marked demolition objects are in the same position and are connected, follow the order of first light and then heavy, first high and then low Sequentially use the crusher for demolition; the driving oil pressure of the crusher is 175kg / cm 2 , The strike frequency is 260bpm, and there is a breaker with a drill rod diameter > 140mm;
[0061] (2) Ground protection: If the original ground or road under the bridge needs to be rebuilt, no ground protection measures shall be taken; if the road under the bridge needs to be used normally after the bridge is demolished, the road surface protection shall be carried out;
[0062] Pavement protection shall be in the form of filling ...