Method of quickly solidifying surface layer of blown filled muck soft foundation
A technology of dredging silt and soft foundation, applied in the direction of infrastructure engineering, construction, etc., can solve the problems of large amount of admixture, large construction risk, pollution, etc., to reduce the cost of auxiliary engineering measures, realize waste utilization, improve The effect of permeability coefficient
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0029] Embodiment 1, a kind of method for rapid consolidation of dredging silt soft base surface layer, its steps are as follows:
[0030] (1) Establish construction passages: designate the dredging silt reinforcement area as the construction area, and build safe construction passages around the construction area. The construction passages are made of positioning piles and foam blocks fixed on the positioning piles;
[0031] (2) Laying non-woven fabrics, drainage boards and filter pipes: Lay 2 layers of non-woven fabrics on the mud surface in the construction area, each layer of non-woven fabrics is wrapped with plastic woven cloth and sewed for reinforcement; lay the first layer of non-woven fabrics After weaving, pass through the first layer of non-woven fabric and insert plastic drainage boards on the silt. The plastic drainage boards in the area are arranged in a square with a spacing of 1.0 meters and a depth of 0.5 meters; 2 layers of non-woven fabrics After the laying i...
Embodiment 2
[0037] Embodiment 2, a kind of method for rapid consolidation of dredging silt soft base surface layer, its steps are as follows:
[0038] (1) Establish construction passages: designate the dredging silt reinforcement area as the construction area, and build safe construction passages around the construction area. The construction passages are made of positioning piles and foam blocks fixed on the positioning piles;
[0039] (2) Laying non-woven fabrics, drainage boards and filter pipes: Lay 2 layers of non-woven fabrics on the mud surface in the construction area, each layer of non-woven fabrics is wrapped with plastic woven cloth and sewed for reinforcement; lay the first layer of non-woven fabrics After weaving, pass through the first layer of non-woven fabric downwards and insert plastic drainage boards on the silt. The plastic drainage boards in the area are arranged in a square with a spacing of 1.0 meters and a depth of 1.5 meters; two layers of non-woven fabrics After ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com