Construction technology of continuous wall on high-water-level boulder layer
A construction technology and high water level technology, applied in the direction of sheet pile wall, foundation structure engineering, foundation structure test, etc., can solve the problems of main structure support, anti-seepage bearing and soil retaining effect that cannot be excavated by subway, etc. Achieve the effect of reducing structural collapse and ensuring the quality of joints
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0031] Embodiment: A construction process for a diaphragm wall in a high water level boulder stratum, comprising: step S1, drilling the cutting box to a designed depth; step S2, building a cement-soil mixing wall with the TRD method; step S3, pulling out the cutting box and disassembling it.
[0032] Step S1, drilling the cutting box to the designed depth. (1) Measure and set off the wire. Before construction, according to the design drawings and the coordinate reference points provided by the owner, accurately calculate the corner point coordinates of the center line of the TRD water-stop curtain (trial wall), use the measuring instrument to stake out, and review the coordinate data, and at the same time do a good job of protection pile. And notify the relevant units to review the release line. (2) Excavate the guide groove according to the equipment weight of the TRD construction method, and after setting out the center line of the water-stop curtain (tested wall) of the T...