A construction method of anti-arching deformation bored pile
A technology of bored piles and construction methods, applied in sheet pile walls, foundation structure engineering, construction, etc., can solve the problems of rock mass creep or rheological deformation, long duration, etc., and achieve convenient construction, high efficiency, The effect of eliminating the influence of adverse frictional resistance
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0019] Below in conjunction with accompanying drawing and embodiment the present invention will be further described:
[0020] refer to figure 1 , figure 2 , a kind of construction method of anti-arching deformation bored pile of the present invention, comprises the following steps:
[0021] ① Position the construction plane of the bored pile 1 on the foundation;
[0022] ②Drilled cast-in-situ pile 1 pile hole construction, use mud to protect the wall until the construction design elevation;
[0023] ③ Make an outer protection pipe 2 matching the pile diameter of the bored pile 1, and the length is equal to the depth from the ground to the boundary line A of the upper arch deformation zone;
[0024] ④ covering and fixing the composite geomembrane 3 on the inner wall of the outer protection pipe 2;
[0025] ⑤ Press the outer protective pipe 2 lined with the composite geomembrane 3 into the pile hole of the bored pile 1, and the nozzle is flush with the ground;
[0026] ⑥T...