Construction method of soil-stone boundary tunnel passing through loess valleys
A technology for tunnel construction and tunneling, which is used in tunnels, tunnel linings, and earth-moving drilling and mining, etc., and can solve problems such as deformation and collapse of tunnel face support.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0165] like figure 1 A construction method of an earth-rock boundary tunnel passing through a loess valley is shown, and the tunnel to be constructed has a cross section greater than 100m 2 And for large-section tunnels that pass through loess gullies, the length of the constructed tunnels is 60m to 100m; Figure 7 , the stratum where the loess gully is located is an earth-rock boundary stratum, and the earth-rock boundary stratum includes a loess layer 3 and a rock layer 4 below the loess layer 3, and the interface between the loess layer 3 and the rock layer 4 is an earth-rock interface The tunnel hole 1 of the constructed tunnel is divided into an upper hole body 1-1, a middle hole body 1-2 and a lower hole body 1-3 from top to bottom, and the upper hole body 1-1 is from the back to the front. The cave body formed after the excavation of the upper steps of the construction tunnel, the middle cave body 1-2 is the cave body formed after the middle step excavation is carried ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com