Dam side boundary control method based on GPS-RTK surveying instrument and programmable calculator
A control method and calculator technology, applied in geometric CAD and other directions, can solve problems such as cost waste, blind backfilling, repeated repairs, etc., and achieve the effects of improving construction accuracy, speeding up construction progress, and reducing measurement error rates
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0068] As an embodiment of the present invention, Xiaomitian Reservoir is a rockfill dam with an asphalt core wall, and it is a comprehensive water conservancy project with the functions of drinking water for residents in Liude Township and Renhe Town, rural people and livestock, agricultural irrigation and water supply for industrial parks. Including hub projects and irrigation canal projects. The reservoir is a medium-sized project. The main structures of the hub project include dams, spillways, spillway tunnels and water tunnels. The normal storage level of the reservoir is 2328.00m, and the corresponding storage capacity is 22.53 million m 3 ; The dam is an asphalt concrete core rockfill dam with a length of 300m and a maximum height of 81.35m.
[0069] Such as Figure 6 As shown, the dam descends from the top of the dam, and the upstream is divided into three abutments, with elevations of 2331.35m, 2311.35m, and 2298.5m. The dam crest is 10m wide, the 2311.35 abutment...
Embodiment 2
[0078]As another embodiment of the present invention, such as Figure 10 , Nalang Reservoir is located in Guangnan County, Wenshan Prefecture, 13km away from the county seat. The total storage capacity of Nalang Reservoir is 1250.71m 3 , which is a medium-sized project, the project class is III, and its main buildings are class III. The dam of Nalang Reservoir is a rockfill dam with a clay core wall, with a height of 49.8m. The crest elevation is 1312.63m, the width is 8.0m, and the dam length is 154.5m.
[0079] The upstream and downstream of the dam are symmetrically divided into three abutments, with elevations of 1312.63m, 1296.83m and 1284.83m respectively. The width of the dam crest is 8m. The width of 1296.83m and 2291.35m is 2.0m. The upstream slope ratio is 1:1.8, and the downstream dam slope is 1:1.7. The first sideline of the dam is the outer sideline of the dry block stone slope protection, and the second sideline is filled with the outer sideline of the rock...
Embodiment 3
[0081] As another embodiment of the present invention, such as Figure 11 , Yuhe Reservoir is a newly built small (one) type reservoir, located in Shuangjiang Town, Eshan County, Yuxi City, Yunnan Province, on the Lvchong River, a second-level tributary of the Eshan Dahe River in the upper reaches of the Qujiang River Basin of the Pearl River System, Yuhe Reservoir provides dam agricultural irrigation for the downstream The backbone water storage project for water use has a dam height of 48.5m and a total storage capacity of 4.19 million m3. The elevation of the dam is 1690.4m, the length of the dam is 130.7m, and the width of the dam is 5.0m. It is a gravel dam with a clay core wall. The upper and lower reaches of the dam are divided into two symmetrical platforms, with elevations of 1690.4m and 1675m respectively. The platform is 2.0m wide. The upstream slope ratios are 1:2.192, 1:2.5, and the downstream dam slopes are 1:1.948, 1:2.25. The first edge of the dam is the out...