Subway station side wall water seepage back grouting plugging method
A backside grouting and subway station technology, applied in the direction of protection devices, infrastructure repair, construction, etc., can solve problems such as incomplete plugging, easy corrosion of structural steel bars, repeated leakage, etc., to improve drainage and grouting effect, speed up the construction, the effect of rapid water leakage
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0020] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
[0021] Such as figure 1 , figure 2 Shown, a kind of subway station side wall seepage water behind grouting sealing method, comprises the following steps:
[0022] a. Select the central position of the seepage water of side wall 1 to drill, the hole diameter is 42mm, and the drilling depth reaches the surface of enclosure structure 2, so that the grouting material spreads around the center of the grouting pipe 4. If the leakage water area is large If the siz...