Tunnel construction method for passing through boundary strata of earth and stone

A technology for tunnel construction and tunneling, which is used in tunnels, tunnel linings, earth-moving drilling, etc., and can solve problems such as deformation of surrounding rock, deformation of face support, and loss of support ability.

Active Publication Date: 2020-04-10
THE NO 6 ENG CO LTD OF CHINA RAILWAY 20TH BUREAU GRP
View PDF6 Cites 4 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

During the actual tunnel construction, the main problems of tunnel excavation in the soil-rock boundary stratum are as follows: first, the hardness of the rock and soil is not uniform, and the blasting of the weathered rock layer in the lower part will easily cause the upper soil layer to collapse, which is harmful to the construction personnel; second, the groundwater The enrichment area further softens the soil-rock boundary strata, causing serious deformation of the surrounding rock; third, the swelling of the expansive soil with water causes the primary support to deform and crack, and in severe cases, the deformed structure of the primary support arch will be damaged and the support capacity will be lost
Once the corresponding reasonable support measures are not adopted in the actual construction or the excavation method is improper, it is very likely to cause deformation of the support in front of the face of the tunnel, and even serious consequences of collapse

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Tunnel construction method for passing through boundary strata of earth and stone
  • Tunnel construction method for passing through boundary strata of earth and stone
  • Tunnel construction method for passing through boundary strata of earth and stone

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0145] Such as figure 1 Shown is a tunnel construction method that crosses the soil-rock boundary stratum, and the tunnel to be constructed has a cross-section greater than 100m 2 And for the shallow buried tunnel located in the soil-rock boundary stratum, the surrounding rock level of the tunnel hole 1 in the constructed tunnel is grade IV or grade V; Figure 7 , the soil-rock boundary stratum includes a loess layer 3 and a rock layer 4 below the loess layer 3, and the interface between the loess layer 3 and the rock layer 4 is an earth-rock interface; the tunnel hole 1 of the constructed tunnel is divided from top to bottom It is an upper cave body 1-1, a middle cave body 1-2 and a lower cave body 1-3. The upper cave body 1-1 is a cave body formed after excavating the upper steps of the constructed tunnel from back to front, The middle cave body 1-2 is a cave body formed after excavating the middle steps of the constructed tunnel from the back to the front, and the lower ca...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a tunnel construction method for passing through the boundary stratum of earth and stone. The tunnel construction method comprises the following steps: I, excavation of a reartunnel segment and initial supporting construction; II, excavation of a middle tunnel segment and initial supporting construction; III, excavation of a front tunnel segment and initial supporting construction, wherein the rear tunnel segment, the middle tunnel segment and the front tunnel segment are all three-step synchronous excavated tunnel segments; and in the process of excavation from rear to front, constructing the secondary lining of the tunnel on the inner side of the initial supporting structure of the constructed tunnel from rear to front. The tunnel construction method has the advantages of reasonable design, simple construction and good use effect. The tunnel construction method selects an appropriate drilling and blasting method according to the position relationship betweenthe earth and stone interface and a tunnel hole, adopts a three-step synchronous excavation way to carry out blasting excavation, can ensure the safe and reliable excavation process of the tunnel passing through the boundary stratum of earth and stone, and can ensure the stable structure of the tunnel. Moreover, in the excavation process, the initial supporting structure and the secondary lining of the tunnel are adopted to provide stable and reliable supporting for the large-section tunnel.

Description

technical field [0001] The invention belongs to the technical field of tunnel construction, and in particular relates to a tunnel construction method for crossing soil-rock boundary strata. Background technique [0002] In the construction process of railway and highway tunnel projects, due to the limitation and influence of geological conditions, it will cause great influence and difficulties to the construction during the construction process. In the process of tunnel construction, various combinations of rock formations are often encountered, such as weak and uneven surrounding rock, shallow buried bias landform, soil-rock mixed geology and so on. For the excavation and support of tunnels that pass through soil-rock mixed strata (also known as soil-rock interface geology or soil-rock boundary strata), at present, the main methods in China are advanced pipe shed grouting support, advanced horizontal jet grouting pile reinforcement, and controlled excavation footage. and o...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E21D9/00E21D11/18E21D11/10E21F16/00
CPCE21D9/00E21D9/006E21D11/18E21D11/10E21D11/107E21D9/001E21F16/00
Inventor 吴小波刘德兵李瑛常运超李世军王存宝张博魏军何精伟李明辉
Owner THE NO 6 ENG CO LTD OF CHINA RAILWAY 20TH BUREAU GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products