Spaced secondary arch frame and long anchor cable lock foot composite construction method for supersoft rock tunnel

A construction method and technology of long anchor cables, which are applied in tunnels, tunnel linings, installation of anchor rods, etc., can solve problems such as deduction of safety and quality credit evaluation, high safety risk of landslide accidents, and impact on the external image of enterprises, so as to reduce construction costs. , the effect of reducing project losses and exempting owners from punishment

Pending Publication Date: 2020-08-25
CHINA RAILWAY 18TH BUREAU GRP CO LTD +1
View PDF8 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] The existing scheme adopts the three-step method + temporary inverted arch, and the secondary lining adopts a double-layer reinforced concrete structure, and the deformation amount of 800-1100mm is reserved, and large extrusion deformation occurs, especially on the left side of the line and the top primary branch encroachment limit. Leading to multiple landslides, repeated rework and arch replacement, slow construction speed, sudden increase in construction costs, and extremely high safety risks in landslide accidents, resulting in deduction of credit points for the safety and quality of the construction unit by the owner, which greatly affected the external image of the company

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Spaced secondary arch frame and long anchor cable lock foot composite construction method for supersoft rock tunnel
  • Spaced secondary arch frame and long anchor cable lock foot composite construction method for supersoft rock tunnel
  • Spaced secondary arch frame and long anchor cable lock foot composite construction method for supersoft rock tunnel

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0022] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0023] The purpose of the present invention is to provide a kind of composite construction method of interspaced secondary arch long anchor cable locking foot of tunnel in extra-soft rock stratum, to solve the problems existing in the above-mentioned prior art, on the basis of the first primary support, by adopting interval The composite method of secondary arch frame and long anchor cable locking feet can avoid the large deformation of the primary support to c...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
Vertical spacingaaaaaaaaaa
Thicknessaaaaaaaaaa
Login to View More

Abstract

The invention discloses a spaced secondary arch frame and long anchor cable lock foot composite construction method for a supersoft rock tunnel, and relates to the technical field of tunnel construction protection. The method comprises: performing construction by a three-step method, wherein the excavated reserved settlement deformation quantity is 500 mm, and advanced small pipes are inserted inthe boundaries of the two side edges and grouting is conducted before middle and lower steps are excavated; a temporary inverted arch primary support is applied after excavation; a grid arch frame isarranged at an interval of 6.0 m; after the two sides of the tunnel are punched by an anchor cable machine, the anchor cable is mounted with 600 mm reserved; grouting is conducted by sulphate aluminium cement, a prestressing force of 3 to 5 tons is applied after solidification for 2 hours, the adjacent two anchor cables are locked by three pairs of anchor cable clamps and are sprayed smoothly withconcrete; and secondary lining is applied by a double-layer reinforced concrete structure to complete construction. On the basis of the first primary support, a composite method of the spaced secondary arch frame and the long anchor cable lock foot is adopted, so that clearance-intrusion, even landslide accident, caused by big deformation of the primary support is avoided, and safety risk is controlled.

Description

technical field [0001] The invention relates to the technical field of tunnel construction protection, in particular to a composite construction method with long anchor cables and locking feet for a tunnel in an extra-soft rock stratum with interval secondary arch frames. Background technique [0002] A high-speed railway double-track tunnel is located in the Jingshan Mountains, which is a structurally denuded low-mountain landform area. The tunnel body passes through the sandy shale of the Xintan Formation (S1x). The tunnel site area is located at the northern edge of the first-order tectonic unit of the Yangtze quasi-platform, within the Shennongjia-Jingmen platform fold belt of the Upper Yangtze continental block fold belt. According to the records of local county annals, earthquakes of magnitude 4.8 or so occurred many times in the area. People felt the ground shaking, their houses were about to collapse, and they fled in panic. watt. The main types of groundwater are...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E21D20/00E21D11/10E21D11/15E21D11/18
CPCE21D20/00E21D11/10E21D11/152E21D11/18Y02E10/20
Inventor 张馨李老三曾德建黄安建郎珉李波
Owner CHINA RAILWAY 18TH BUREAU GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products