Unlock instant, AI-driven research and patent intelligence for your innovation.

Post-closed outer wall post-cast strip reinforcement construction method

A construction method and post-casting belt technology, which are applied in the directions of manufacturing tools, building components, ceramic molding machines, etc., can solve the problems of increasing the complexity of the construction process, time-consuming post-casting belt reinforcement and pouring, and increasing construction costs, etc., and achieve high-efficiency prefabrication. The effect of processing efficiency, excellent appearance quality and efficient construction

Inactive Publication Date: 2020-12-22
CCFED THE FIGTH CONSTR & ENG
View PDF10 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Since the construction of the post-pouring belt involves secondary operations, it not only actually increases the complexity of the construction process, but also affects the construction progress and increases the construction cost.
Therefore, there is an urgent need for an efficient and economical technical solution to solve the time-consuming and labor-intensive technical problems of consolidating and pouring such post-casting belts after they are closed in advance.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Post-closed outer wall post-cast strip reinforcement construction method
  • Post-closed outer wall post-cast strip reinforcement construction method
  • Post-closed outer wall post-cast strip reinforcement construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0036] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are only some embodiments of the present invention, rather than all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention.

[0037] see Figure 1-4 As shown, a post-enclosed external wall post-pouring tape reinforcement construction method includes the following steps,

[0038] Step 1: Design the concrete precast block mold according to the size of the concrete precast block, build and install the concrete precast block mold according to the requirements of the design and construction specifications, and use the precast block to provide a relatively stable appearance quality and high prefabrication processing efficiency for the wall veneer of ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a post-closed outer wall post-cast strip reinforcement construction method. The method comprises the following steps that a concrete precast block mold is designed according tothe size of a concrete precast block, and the concrete precast block mold is built and installed according to design and construction specification requirements; and transverse steel bars and longitudinal steel bars are laid in the concrete precast block mold, then a plurality of connecting nuts are pre-buried in one end of the concrete precast block mold, reinforcing steel bars are laid on the two sides of the connecting nuts, the reinforcing steel bars and the transverse steel bars are bound and connected, then the connecting nuts and the reinforcing steel bars are welded and fixed, and lifting rings are pre-buried in the two sides of the concrete precast block mold. According to the construction method, the construction cost is reduced, the consumption of turnover materials is reduced,the post-cast strip is safely and reliably closed in advance, the construction progress is accelerated, energy conservation and environmental protection are achieved, meanwhile, the construction process is simple in manufacturing, flexible in operation and high in efficiency, the cost is reduced, the efficiency is improved, and then the technical problem that time and labor are wasted during reinforcement pouring after the post-cast strip is closed in advance is solved.

Description

technical field [0001] The invention belongs to the technical field of building construction, and relates to a construction method for reinforcing a post-casting belt of a rear-closed outer wall. Background technique [0002] The post-pouring belt is a temporary construction joint set in the building. The joint is reserved for a period of time before pouring, that is, the original "extra long" plane is "divided into parts" so that it can be completed in a short period of time The shrinkage of concrete, the release of restraint stress such as deformation caused by excessive vertical load difference. After the construction of the post-cast belt is completed, the structure will be "turned into a whole", which greatly reduces the influence of the above stress on the structure and reduces the excessive setting of permanent deformation joints. This kind of "seam" not only solves the differential settlement between buildings, but also solves the shrinkage deformation of concrete a...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E04B1/682B28B1/093B28B23/00B28B23/02
CPCB28B1/093B28B23/00B28B23/02E04B1/68E04B1/6801E04B1/6806
Inventor 杨昌顺王浪邹闵武李丹钟强吴军
Owner CCFED THE FIGTH CONSTR & ENG