A prestressed cable-stayed hanging basket installation method and installation structure
An installation method and prestressing technology, applied in the direction of building structure support, building structure support, building structure support scaffolding, etc., can solve the problems of poor sealing of openings, inability to construct outer eaves, and high erection height, so as to improve construction efficiency and construction effect, improve the safety of use, and the effect of convenient construction
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0035] The installation method of the prestressed cable-stayed hanging basket of the present invention, such as figure 1 , including the following steps,
[0036] Prestressed triangular bracket processing: According to the model of the selected hanging basket, carry out the structural design of the prestressed triangular bracket, select the steel material of appropriate specifications for blanking, weld the channel steel main beam 7 and the channel steel inclined beam 8, and Weld the channel steel main beam 7, channel steel inclined beam 8 and anchor plate 9, and weld the channel steel main beam 7, channel steel inclined beam 8 and stiffener 11; fix the ring at one end of the turnbuckle bolt 6 on the stiffener 11 ; Bolt holes 13 are provided on the anchor plate 9;
[0037] Said prestressed triangular bracket lifting test: install said prestressed triangular bracket on a test frame, and hang heavy objects on the stiffeners 11 of said hanging basket to carry out load test;
[...
Embodiment 2
[0046] In the installation method of the prestressed cable-stayed hanging basket described in Embodiment 1, when the main rope 12 of the hanging basket is fixed on the stiffener 11, the main rope 12 of the hanging basket is fixed on the stiffener 11 through a wire rope clamp.
[0047] It may further be possible to clean up the site after removing the hanging basket and the prestressed triangular support.
[0048] Furthermore, after the site is cleaned, the bolt holes 13 are cleaned and blocked: the bolt holes 13 are cleaned on the roof side, and the bolt holes 13 are blocked.
[0049] Furthermore, when the bolt holes 13 are sealed, waterproof mortar, styrofoam and waterproof tape are used to seal the bolt holes 13 .
[0050] Furthermore, after the bolt holes 13 are cleaned and blocked, the outer eaves are repaired: the outer eaves insulation layer and paint at the prestressed triangular bracket are repaired.
[0051] It is also possible to further set a limiting plate at the ...
Embodiment 3
[0058] A prestressed cable-stayed hanging basket installation structure, which is constructed by the prestressed cable-stayed hanging basket installation method described in embodiment 1 or embodiment 2, such as Figure 2 to Figure 4 , including transverse channel steel girders 7, longitudinal anchor plates 9, oblique channel steel beams 8, embedded casings 5, eyebolts 2, turnbuckle bolts 6, anchor bolts 10, anti-slip gaskets 4 and double nuts 3. The channel steel main beam 7, the anchor plate 9 and the channel steel inclined beam 8 are sequentially connected end to end to form a prestressed triangular bracket; the embedded casing 5 and the eyebolt 2 are fixed on the pergola beam 1 or the shear wall structure; The prestressed triangular bracket and the eyebolt 2 are connected by turnbuckle bolts 6; the prestressed triangular bracket and the flower frame beam 1 or the shear wall structure are connected by anchor bolts 10; both sides of the prestressed triangular bracket are inst...