Deformation automatic monitoring and early warning method that can be used in high fill and soft foundation engineering
A monitoring and early warning, deformation monitoring technology, applied in the fields of infrastructure engineering, on-site foundation soil survey, alarms, etc., can solve the problems of damage to monitoring instruments, difficulty in burying and implementation, and low monitoring accuracy, and achieve low interference, Ensuring stable and high measurement accuracy
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0050] Such as figure 1 and figure 2 As shown, the present invention discloses an automatic deformation monitoring and early warning method that can be used in high fill and soft foundation engineering, which is characterized in that it includes:
[0051] Before carrying out the filling construction on the monitored soft soil layer 2, the following steps 1 to 5 are completed, wherein the filling construction is used to form the monitored filling 1 on the monitored soft soil layer 2:
[0052] Step 1, use a drilling machine to drill down into and out of the borehole 2a on the ground of the monitored soft soil layer 2, the borehole 2a is located at the axis of the monitored fill 1, and the borehole 2a goes deep into the monitored soft soil layer 2 Monitoring the underlying layer of the soft soil layer 2 (that is, the rock-soil layer 3 that is incompressible or has a negligible amount of compression); wherein, the position of the borehole is not required to be coaxial with the a...
Embodiment approach
[0064] The deformation automatic monitoring and early warning method also includes:
[0065] Before carrying out filling construction on the monitored soft soil layer 2, complete the following step six:
[0066] Step 6, fixing the first end of the wire rope 7 on the reference pile 4, and leading the second end out of the range of the monitored fill 1;
[0067] Before carrying out the filling construction on the monitored soft soil layer 2 or during the filling construction, complete the following steps 7 to 9:
[0068] Step 7: Bury the displacement pile 8 between the toe 1-1 of the monitored fill 1 and the outlet of the potential slip surface 1-2 of the monitored fill 1, and make the displacement pile 8 The top of the exposed above the ground of the monitored soft soil layer 2; wherein, the outlet of the potential slip surface 1-2 refers to the potential slip surface 1-2 and the monitored soft soil layer 2 The junction of the ground. The displacement pile 8 can be a steel p...
Embodiment 3
[0077] On the basis of the above-mentioned embodiment two, the present embodiment three also adopts the following preferred implementation modes:
[0078] The deformation monitoring system includes a settlement deformation data acquisition instrument, a slope deformation data acquisition instrument and a power supply system, and the settlement deformation data acquisition instrument and the slope deformation data acquisition instrument are all provided with a single-chip microcomputer, an Internet of Things module and a Bluetooth module, the single-chip microcomputer of the settlement deformation data acquisition instrument can receive and store the settlement deformation data collected by the vertical displacement sensor 6, and the single-chip microcomputer of the slope deformation data acquisition instrument can receive and store the horizontal displacement sensor 9. For the collected slope deformation data, both the settlement deformation data acquisition instrument and the ...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 

