Foundation pit dewatering construction method based on super pressure-suction combined water pumping system
A construction method and technology of drainage system, applied in infrastructure engineering, construction, etc., can solve the problems of low precipitation effect, low applicability, low precipitation efficiency, etc., and achieve improved precipitation effect, large applicability, and high precipitation efficiency. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0045] The specific implementation manners of the embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings. It should be understood that the specific embodiments described here are only used to illustrate and explain the present invention, and are not intended to limit the present invention.
[0046] refer to figure 1 ,figure 1 It is a schematic flow chart of an embodiment of the foundation pit dewatering construction method based on the super pressure-suction combined pumping system of the present invention, the method includes the following steps:
[0047] 101. Well completion construction: determine the drilling well position and the pre-calculated well spacing for excavating the foundation pit, and vertically bury the pre-prepared hole protection pipe into the undisturbed soil of the drilling well position according to the depth of 10cm-20cm, and pass the approaching The drilling rig, according to the mud specifi...
PUM
| Property | Measurement | Unit |
|---|---|---|
| Height | aaaaa | aaaaa |
| Width | aaaaa | aaaaa |
| Height | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
Login to View More 