Unlock instant, AI-driven research and patent intelligence for your innovation.

Electrified acceptance system of one-key sequence control system

A technology of sequential control and simulation system, applied in the field of electric power equipment, can solve the problems of human and material resource consumption, short power outage window, affecting the stability of the power grid, etc.

Pending Publication Date: 2021-08-31
国网冀北电力有限公司超高压分公司 +1
View PDF7 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The power outage mode of the whole station or the interval wheel stop brings great manpower and material resources consumption, and even affects the stability of the power grid. At the same time, all or part of the electric quantity of the station is zero under the power outage condition, which is not conducive to judging whether the equipment is operating or not based on the remote measurement of the equipment. in place
[0004] At present, there are no practical application solutions for a series of problems in the one-key sequence control transformation of 500kV and above substations, such as short power outage window and inability to carry out actual transmission, that is, there is currently no corresponding solution to realize the one-key sequence control system of intelligent stations Live debugging, so that it is impossible to judge whether the device is operating properly according to the remote measurement of the device

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Electrified acceptance system of one-key sequence control system
  • Electrified acceptance system of one-key sequence control system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0024] figure 1 It is a block diagram of a live acceptance system of a one-button sequential control system according to the embodiment of this application.

[0025] Such as figure 1 As shown, the live acceptance inspection system provided by this embodiment is applied to a smart substation, and is used for live inspection and acceptance of the one-key sequential control system 100 of the smart substation, specifically including a joint acceptance platform 10 connected to the one-key sequential control system. The acceptance platform includes a substation MMS simulation system 11 and an auxiliary decision verification system 12 .

[0026] The one-button sequential control system described in this application refers to a software prefabrication of operation items, modular construction of operation tasks, automatic identification of equipment status, intelligent verification of error-proof interlocking, one-key start of operation steps, and automatic sequence of operation proce...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an electrified acceptance system of a one-key sequence control system, wherein the system is applied to an intelligent transformer substation and comprises a joint acceptance platform, and the joint acceptance platform comprises a transformer substation MMS simulation system and an auxiliary judgment verification system. The transformer substation MMS simulation system is used for a simulation environment consistent with the operation characteristics of a to-be-verified one-key sequence control system, and the one-key sequence control system comprises a sequence control host; and the auxiliary judgment verification system is used for simulating the switching-on and switching-off change of primary equipment of the intelligent transformer substation based on primary simulation equipment, realizing multi-angle, multi-scene and multi-environment simulation of the switching-on and switching-off position posture change of the primary equipment, and sending result information after posture recognition of the primary equipment to the sequence control host. According to the system, the electrified debugging of the opinion sequence control system can be realized, so that whether the equipment is operated in place or not can be judged according to the equipment remote measurement quantity.

Description

technical field [0001] The present application relates to the technical field of electric power equipment, and more specifically, relates to a live-in inspection system of a one-button sequential control system. Background technique [0002] In the domestic power industry, with image recognition and attitude sensing related technologies becoming more mature and widely used, the one-button sequential control mode is gradually replacing manual switching operations of conventional substation equipment. In the past two years, in conventional converter stations and flexible converter stations, the one-key sequence control system is generally installed, debugged, and put into operation synchronously with the main equipment during infrastructure construction to ensure the correctness of the one-key sequence control system. [0003] Smart substations that carry out one-button sequence control transformation at home and abroad often use the power outage mode of the whole station or t...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G01R31/00H02J13/00
CPCG01R31/00H02J13/00016Y04S40/124Y02E60/00
Inventor 李广渊李钟凯李世群蒲鑫郭飞顾颖宋巍
Owner 国网冀北电力有限公司超高压分公司