An underground garage and permanent support technology, applied in the direction of underwater structures, soil protection, construction, etc., can solve the problem of insufficient parking spaces, the underground garage cannot fully utilize the building, and can only be used for placement equipment or other purposes and other problems, to achieve the effect of good embedding, wide driving passage, and increasing the usable area
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0034] This embodiment provides an underground garage system that adopts permanent support to increase the usable area, such as Figure 1-Figure 3 As shown, it includes soil-squeezing piles 2, ground connecting walls 3, and column nets 4. Soil-squeezing piles 2 are arranged at intervals along the ground red line 1, and ground connecting walls 3 are set between adjacent soil-squeezing piles 2, and underground garages are arranged inside the land red line 1. Column grid 4.
[0035] Further, the soil-squeezing piles 2 are embedded with steel plates or reserved steel bar joints in advance during prefabrication, and the distance between adjacent soil-squeezing piles 2 is determined according to the size of the designed garage column network 4, so as to facilitate connection with the underground garage column network 4. Extrusion reduces the volume of the soil around the foundation pit, increases the density, increases the effective stress of the soil, and strengthens the embedding ...
Embodiment 2
[0039] This embodiment provides a construction method for an underground garage system that uses permanent support to increase the usable area. The edge of the land red line 1 is used as the design position of the underground garage, and the column network 4 is constructed according to the design position, and the column network 4 is connected to the ground. The wall 3 is connected; wherein, before the excavation of the soil, the ground red line 1 is used to construct the soil squeezing pile 2; afterward, the ground connection wall 3 is constructed in sections, and the ground connection wall 3 is used as the outer wall of the underground garage; the ground connection wall 3, The soil squeezing pile 2 and the column network 4 form a stable whole.
[0040] Specifically, the following steps are included:
[0041] (1) Design the location of the underground garage:
[0042] In the design stage of the underground garage, the specific location of the underground garage is determined...