Construction method for lap-joint correction connection of reinforcement cages
A construction method and steel cage technology, which is applied in manufacturing tools, welding equipment, metal processing, etc., can solve the problems of steel bar correction, difficult to achieve site conditions, and inaccurate alignment, so as to meet the requirements of connection accuracy, reduce construction difficulty, and high efficiency effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0029] Such as Figure 1 to Figure 5 As shown, the present embodiment is used for the construction method of steel cage overlap correction connection, and this construction method comprises the following steps:
[0030] Step 1: Roughly align the No. 1 lap joint 11 on the No. 1 steel bar 1 and the No. 2 lap 21 on the No. 2 steel bar 2, and keep the partial joints of the two steel cages The direction of the steel bar is straight;
[0031] Second step: open the crimping joint 32 of the manual hydraulic clamp 3, and clamp the No. 1 lap joint 11 on the No. 1 reinforcement cage reinforcement bar 1 and the No. 2 lap joint 21 on the No. 2 reinforcement cage reinforcement bar 2 two reinforcements, Close the crimping head 32, insert the pin 33, manually press the hydraulic handle 35, and squeeze the two separated No. Alignment of a joint bar between cage bar 1 and No. 2 cage bar 2;
[0032] Step 3: Then the No. 1 lap 11 and the No. 2 lap 21 steel bars are welded and fixed with weldin...
Embodiment 2
[0040] The structure of the construction method used in this embodiment for the rectification and connection of the steel cage overlap is basically the same as the structure of the construction method for the construction method of the reinforcement cage lap correction connection in Embodiment 1, the difference is that the hanging mechanism 5 includes a fixed Plate 51, support plate 52, fixing bolt 53, support screw rod 54 and support bracket 55 (see Figure 6 and Figure 7 ). The top of the fixed plate 51 is provided with a support plate 52, the fixed plate 51 on the outside of the support plate 52 is provided with a fixed bolt 53, the support screw 54 is threadedly installed on the support plate 52, and one side of the support screw 54 runs through the support plate 52 for fixed installation. Bracket 55, the fixed plate 51 is fixedly installed on the top of the pile hole 6 by the fixing bolt 53, which is convenient for the fixing of the reinforcement cage unit section in th...