Low-position vacuum preloading rapid reinforcement method of soft foundation in hydraulic filling and reclamation

A soft foundation, land reclamation technology, applied in soil protection, infrastructure engineering, construction, etc.

Inactive Publication Date: 2013-04-10
徐云童
View PDF16 Cites 11 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The above-mentioned technical schemes all still adopt the high-level drainage method of blowing and filling first, and then laying drainage boards and laying drainage pipe networks. The common problems that exist are: 1. Since the drainage boards are manually or mechanically inserted after the completion of the blowing and filling process , so it is still necessary to carry out surface treatment on the dredged silt layer, such as laying geotextiles, making thorn rakes or bamboo rakes, laying engineering sand or silt, etc., to meet the requirements of the drainage board laying machinery entering the site; 2. Due to Drainage boards need to be installed vertically in the dredged sludge, and special drainage board drilling machines are required, which will inevitably make the operating procedures more cumbersome and complicated, labor-intensive, and greatly increase the cost of drainage and solidification of dredged sludge; 3. When plugging the drainage board and encountering muddy soil, the drainage board will rub against the mud, smear the filter cloth wrapped by the drainage board, and close the gap of the filter cloth, which will obviously reduce the vacuum drainage efficiency and increase the drainage cost; 4. After a lot of scientific calculations and engineering practice, it has been proved that the vacuum equipment used at home and abroad at present, the vacuum degree of the vacuumed soft base membrane is zero below 2m, and the water below the membrane is squeezed out by superstatic pressure.
Therefore, the high-level drainage method is not suitable for dredging and filling the silt drainage reinforcement with a depth of more than 2m.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Low-position vacuum preloading rapid reinforcement method of soft foundation in hydraulic filling and reclamation
  • Low-position vacuum preloading rapid reinforcement method of soft foundation in hydraulic filling and reclamation
  • Low-position vacuum preloading rapid reinforcement method of soft foundation in hydraulic filling and reclamation

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0074] When the final dredging design elevation is 1m, according to the attached Figure 1-5 As shown in the content, only the bottom drainage pipe network can be set to meet the needs of drainage consolidation. The specific technical scheme is as follows

[0075] 1. The layout of the bottom drainage pipe network

[0076] Before the dredging and filling of sludge, the laying of the bottom drainage pipe network 16 is carried out. The spacing of the permeable holes 12 on the surface of the drain pipe is 2m. In order to prevent the entry of mud, the outer surface of the permeable hole on the drain pipe is wrapped with non-woven fabric. On the ground surface 6 of the area to be filled, a commercially available conventional drainage board 5 and the permeable hole of the drainage pipe 1 are used for wrapping and fixing.

[0077] The horizontal spacing b of adjacent brackets in the single row of brackets in the drainage pipe network is 2m, and the horizontal row spacing a of adja...

Embodiment 2

[0093] When the final dredging design elevation is 1.5m, according to the attached Figure 1-5 The content shown is set to a total of two layers of drainage pipe network, the bottom layer and the upper layer. The specific technical scheme is as follows:

[0094] 1. The layout of the bottom drainage pipe network

[0095] Before dredging and filling the sludge, lay out the bottom drainage pipe network according to the method of Example 1. The distance between the permeable holes 12 on the surface of the drainage pipe is 3m, the horizontal distance between adjacent drainage pipes is 6m, and the horizontal distance between adjacent drainage branch pipes is 30m.

[0096] 2. Arrangement of brackets

[0097] Before dredging and filling the mud, the ground surface 6 of the area to be filled is horizontally set up supports 9 side by side. The bracket is composed of three bamboo poles, the lower ends of which are inserted into the ground surface, and the upper ends of the brackets i...

Embodiment 3

[0113] When the final dredging design elevation is 4m, according to the attached Figure 1-5 The content shown is set to a total of two layers of drainage pipe network, the bottom layer and the upper layer. The specific technical scheme is as follows:

[0114] 1. The layout of the bottom drainage pipe network

[0115] Before dredging and filling the sludge, lay out the bottom drainage pipe network according to the method of Example 1. The distance between the permeable holes 12 on the surface of the drainage pipe is 1.5m, the horizontal distance between adjacent drainage pipes is 4m, and the horizontal distance between adjacent drainage branch pipes is 20m.

[0116] 2. Arrangement of brackets

[0117] Before dredging and filling the mud, the ground surface 6 of the area to be filled is horizontally set up supports 9 side by side. The bracket is composed of three metal pipes, the lower ends of which are inserted into the ground surface, and the upper ends of the brackets in...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a low-position vacuum pre-pressing rapid reinforcement method of a soft foundation in hydraulic filling and reclamation and relates to a drainage and reinforcement method of hydraulic fill sludge in a hydraulic filling and reclamation project. According to a single drainage and reinforcement unit, conventional drainage boards are used and are connected with drainage pipes; the connection between the drainage pipes and drainage branch pipes, the connection between the drainage branch pipes and a drainage trunk pipe and the connection between the drainage trunk pipe and a drainage main pipe are realized by adopting a conventional method; and then the drainage main pipe is connected with drainage equipment by adopting the conventional method to form a drainage pipe network. After hydraulic filling, a covering layer is laid on the surface of a sludge layer and water permeation prevention treatment is conducted. The drainage pipe network is arranged in a hydraulic filling sludge layer and can be horizontally arranged in a single layer, two layers or more than two layers. Meanwhile, drained water is used as a piling carrier to preload the hydraulic filling sludge. By adopting a simple construction method of combining low-position drainage with high-position drainage in the technical scheme, the construction operation difficulty is greatly reduced, the draining efficiency of hydraulic filling sludge is improved, and the construction cost and the construction period are greatly reduced.

Description

technical field [0001] The invention relates to a drainage solidification method for dredging and filling mud in a dredging and land reclamation project. Background technique [0002] Before the realization of the method of the present invention, with the rapid development of the country's economy, the contradiction between the land for infrastructure construction and the protection of basic farmland became more prominent. A large-scale land reclamation project was carried out. The basic method of land reclamation is to blow and fill the seabed silt to a predetermined area through special equipment, and then perform drainage and solidification treatment on the blow-filled silt to make it meet the requirements of construction land. The most primitive method of land reclamation is natural drying and solidification after dredging to make the water in the dredged sludge evaporate gradually, or to lay out drainage ditches in the dredged sludge layer so that the water in the dred...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D3/10
Inventor 徐云童
Owner 徐云童
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products