Stability augmentation and solidification method for large-section water-rich saturation fine-silt railway tunnel

A technology with fine sand and large cross-section, which is applied in the field of reinforcement and consolidation of large cross-section water-rich and saturated fine sand railway tunnels. It can solve problems such as shotcrete cracking, open welding of steel frames and longitudinal connecting bars, and uneven convergence deformation. Achieve the effect of ensuring construction safety, improving overall stability and improving construction quality

Inactive Publication Date: 2014-03-12
CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP
View PDF4 Cites 6 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

During the construction of the test section, it was found that due to the uneven convergence and deformation of the steel frame settlement, the welding between the steel frame and the longitudinal

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Stability augmentation and solidification method for large-section water-rich saturation fine-silt railway tunnel
  • Stability augmentation and solidification method for large-section water-rich saturation fine-silt railway tunnel
  • Stability augmentation and solidification method for large-section water-rich saturation fine-silt railway tunnel

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0036] Such as figure 1 Shown: a method for increasing the stability of a large-section water-rich saturated silt-fine sand railway tunnel, including the following steps:

[0037] 1. Precipitation in advance: use the 5.3m-high double-side wall pilot tunnel to construct the lower half section of the front tunnel ahead of time, adopt the method of "vacuum light well point dewatering + filter sump pit collection and drainage", the length of φ32mm PPR tube well is 4-5m, and V6 is selected A type vacuum pump (7.5KW) carries out advanced drainage of the pilot tunnel in steps, and the vacuum dewatering main pipe guides and drains the water to the filter sump for centralized pumping and drainage. According to the construction summary of the field test section, the precipitation effect should satisfy the fact that the sand layer is slightly wet but no clear water seepage is the best when the face is excavated. At this time, the measured moisture content of the sand is 5-8%. The above-...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

A stability augmentation and solidification method for a large-section water-rich saturation fine-silt railway tunnel comprises the following steps that (1) advance dewatering is conducted by means of a double-side-wall advance pilot tunnel on the lower portion of the tunnel, and dewatering and solidification are conducted on a construction sand layer of the tunnel; (2) partial excavation is conducted, vertical steel frames are erected, the lower pilot tunnel is excavated in an upper and lower step core soil reserve method, the vertical steel frames are erected longitudinally, the whole ring of the primarily-erected steel frame of a main tunnel is divided into a plurality of units, and steel boards are utilized as flanges among the units and are connected through high-strength bolts; (3), fore shaft anchor pipes are fixedly connected to the steel frame connection boards, the anchor pipes are welded to the steel frames, the anchor pipes are filled with mortar, the steel frame connection boards are fixedly connected with longitudinal connection U-steel, and longitudinal connection reinforcing steel bars among the steel frames are distributed in a Z shape; (4) cement single fluid is poured to the back of the primarily-erected steel frame timely in a pressing mode after excavation is completed, and grouting and solidifying are conducted on the disturbed sand layer. According to the stability augmentation and solidification method, self-bearing ability of surrounding rock can be enhanced, and therefore construction safety is guaranteed.

Description

Technical field: [0001] The invention belongs to a tunnel engineering construction method, in particular to a method for increasing stability and consolidation of a large-section water-rich saturated silty sand railway tunnel. Background technique: [0002] The geological conditions of water-rich and saturated silt-fine sand strata determine the particularity of tunnel construction. At present, it is rare to build tunnels in water-rich and saturated silt-fine sand stratum in China, and there is no corresponding construction experience for reference. [0003] The conventional method for constructing tunnels in water-rich and saturated silt fine sand strata is to excavate in sections to strengthen the rigidity of the initial support steel frame. Excavation. However, since the original sand layer is dense without excavation and disturbance, the grout diffusion range is very limited, and the grouting consolidation effect is poor, and sand gushes and slides still occur during ex...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E21D9/00E21D11/10
Inventor 赵旭鹏李素清张学文王平王锋刘绍石李子明
Owner CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products