Intermittent supercritical unit stabilized-pressure pipe blowing method
A supercritical unit and intermittent technology, which is applied in the field of thermal power plants, can solve the problems of increasing fuel consumption, the total number of blowing pipes, and the temperature change of the water storage tank, etc., and achieves the effect of saving fuel consumption and shortening the construction period.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0014] In the supercritical boiler blowpipe process, first use the time of warm grinding, use the energy storage decompression method to blowpipe, through the cold and heat conversion of the pipeline, the pipeline is initially purged; The pipeline is fully purged by the method, and the target is qualified after stepping down. During the blowing period, the furnace does not stop and the flame is not turned off. When the pressure-stabilized blowpipe is used for 2 hours or the desalinated water consumption is close to 2000t, the method is changed to the energy storage depressurization method, and the pipeline is purged 5 to 10 times according to the control of temperature and pressure. ; Then change to a constant pressure blowpipe, and when the constant pressure blowpipe continues for 2 hours or when the desalinated water volume is close to 1000t / h, then gradually change to a reduced pressure blowpipe, and reduce the pressure to shoot until the target is qualified.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com