Problems solved by technology

[0004] The purpose of the present invention is to provide a T-shaped rigid jointed limb wall with pre-embedded jointed beam sections and its construction method, to solve the problems of complex stress, unstable structure, unreliable connection relationship and inconvenient construction of traditional structures. technical problem

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • T-shaped rigid seam coupled wall with pre-embedded seam beam segment, and construction method thereof
  • T-shaped rigid seam coupled wall with pre-embedded seam beam segment, and construction method thereof
  • T-shaped rigid seam coupled wall with pre-embedded seam beam segment, and construction method thereof

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0092] Examples see image 3 , Figure 4 As shown, this T-shaped rigid jointed limb wall with pre-embedded joint beam sections includes a first wall unit and a second wall unit that are vertically connected to each other to form a T shape, and the first wall unit and the second wall unit are both prefabricated components, the concrete strength grade is not less than C30 and not higher than C60, the height of the wall is about the floor height minus the thickness of the floor slab, and the two are connected by a joint post-casting tape, the joint Post-pouring belt 3 comprises joint post-casting concrete 30 and the joint post-casting vertical reinforcement 31 and joint post-casting stirrup 32 poured inside the joint post-casting concrete, and the joint post-casting concrete strength level It should be two grades or more higher than the concrete strength grade of the first wall unit and the second wall unit.

[0093] see figure 1 , figure 2 As shown, the first wall unit incl...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a T-shaped rigid seam coupled wall with a pre-embedded seam beam segment, and a construction method thereof. The coupled wall comprises a first wall unit and a second wall unit which are mutually vertically connected and form a T shape, wherein the first wall unit and the second wall unit are both prefabricated members and the two are connected through a seam post-cast strip. The node connection is safe and reliable, the antivibration performance is good, and at the same time, factory fabrication and onsite installation are also carried out simultaneously; and wall assembling units are prefabricated in a factory, splicing installation is performed in a field, structural members are manufactured and installed at the same time, the construction speed of a main body structure is improved, it is guaranteed that a construction project is completed on schedule, in a construction process, through structural assembling and combination, the wet construction amount of a concrete field is reduced, the application quantities of templates and temporary supports are reduced, building garbage is reduced, the requirements for saving materials and protecting environment are realized, and the purpose of green construction is ahiceved.

Description

technical field [0001] The invention relates to the field of building construction, in particular to an assembled wall pier structure and a construction method thereof. Background technique [0002] The high-rise building structure is an inevitable choice to solve the contradiction between the growing urban population and the gradual shortage of urban land in the process of urbanization in my country, and the connected wall structure system is an indispensable element in the high-rise building structure. According to the measured data in the past, the attached wall system not only inherits the advantages of simple shear wall engineering such as low cost and high lateral stiffness, but also reflects the yield energy consumption of the connecting beam under the action of strong earthquakes, avoiding or reducing a large number of cracks concentrated in the The situation at the bottom of the wall has the advantage of reducing the cost of post-earthquake repairs. [0003] Howeve...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E04B2/58E04B2/60E04B2/56
CPCE04B2/56E04B2/58E04B2/60
Inventor 肖绪文卢海陆石敬斌冯大阔张东华张旭乔马瑞江
Owner CHINA STATE CONSTRUCTION ENGINEERING CORPORATION
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products