Installation method of the door frame of the sluice gate of ap1000 nuclear power plant
An installation method and technology of water gates, which are applied in water conservancy projects, sea area projects, construction, etc., can solve the problems of difficult control of inert gas, poor welding quality, and high construction costs in the size of door frames and door openings, so as to reduce construction costs and ensure welding efficiency , Improve the effect of construction efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0037] The technical solutions in the present invention will be described in detail below in conjunction with the accompanying drawings.
[0038] combine figure 1 , figure 2 and image 3 As shown, using the AP1000 nuclear power plant sluice door frame installation method of the present invention, the specific steps for installing and fixing the door frame 1 and the door opening 2 of the sluice door are as follows:
[0039] The first step is to measure the size of the door opening 2. Due to the high sealing requirements between the door frame 1 and the door opening 2, in the AP1000 nuclear power plant, the door opening 2 is also made of metal material, and is fixedly connected to the door frame 1 by welding, and because the height of the door opening 2 Very large, exceeding the height dimension of the door frame 1. In this way, during the installation process of the door opening 2 , it is unavoidable to have dimensional deformation and deviation, especially along the width...