Unlock instant, AI-driven research and patent intelligence for your innovation.

Construction method of split-through concrete pouring with full-hydraulic self-propelled formwork trolley

A formwork trolley and construction method technology, which is applied in earthwork drilling, shaft equipment, wellbore lining, etc., can solve the problems of cumbersome procedures, high safety risks, and many operators

Active Publication Date: 2019-02-15
CHINA RAILWAY TUNNEL GROUP CO LTD +1
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, it takes a long time to build, the process is cumbersome, there are many operators, and there is a lot of mutual interference, which is labor-intensive and time-consuming.
During manual construction, there are many uncontrollable safety factors, high safety risks, and difficult management
The conventional integral hydraulic formwork trolley is used for construction. When walking, the upright column and the lower turning beam cannot be avoided. Moreover, because the concrete thickness of the middle plate and the roof plate is thick, it takes a long time for the concrete to solidify to reach the demoulding strength, and the formwork trolley enters the next step. The cycle takes too long, seriously affecting the construction period

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of split-through concrete pouring with full-hydraulic self-propelled formwork trolley
  • Construction method of split-through concrete pouring with full-hydraulic self-propelled formwork trolley
  • Construction method of split-through concrete pouring with full-hydraulic self-propelled formwork trolley

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0019] The technical solution of the present invention will be described in further detail below in conjunction with the accompanying drawings and embodiments.

[0020] Such as figure 1 , 2 , 3, the construction method of the present invention is described in detail with two formwork trolley groups as an example.

[0021] The first formwork trolley section A is composed of a single full hydraulic self-propelled formwork trolley A1, a single full hydraulic self-propelled formwork trolley A2, and a single full hydraulic self-propelled formwork trolley A3, and the second formwork trolley section B It consists of a single fully hydraulic self-propelled formwork trolley B1, a single fully hydraulic self-propelled formwork trolley B2, and a single fully hydraulic self-propelled formwork trolley B3.

[0022] The fully hydraulic self-propelled formwork trolley carries out the construction method of split-through concrete pouring, which includes the following specific steps:

[0023...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a split crossing type concrete casting construction method of a full-hydraulic self-walking formwork trolley. According to the inner profile size of a middle plate and a top plate of the section of a required building structure and the distribution of middle columns, a formwork trolley group section of two or more single-body full-hydraulic self-walking formwork trolleys is arranged; according to the segmented form of the length structure of the building structure and the construction cycle time of concrete meeting demolding strength, two or more formwork trolley group sections are arranged, and crossing alternating concrete construction is conducted. The method is used in urban underground metro section and station lining concrete construction, the problem that concrete does not meet the requirement of demolding strength and demolding can not be conducted is solved, construction speed is not influenced, higher smoothness is achieved, the steel-structure formwork trolley meets the requirement of variable section and variable width, construction is more convenient, controllability is higher, and the efficiency of work, material and machine is improved.

Description

technical field [0001] The invention belongs to the technical field of underground engineering construction, and in particular relates to a split-through concrete pouring construction method performed by a fully hydraulic self-propelled formwork trolley. Background technique [0002] At present, in the concrete construction of subway sections and station linings underground in cities, the middle and roof spans are large and variable, there are columns in the middle, and upturned beams are placed on the bottom plate, so the formwork construction requirements are more adaptable. The concrete construction of the middle plate and roof lining usually adopts steel pipe scaffolding or buckle scaffolding as the supporting system, and the formwork is laid. However, it takes a long time to build, the process is cumbersome, there are many operators, and there is a lot of mutual interference, which is labor-intensive and time-consuming. During manual construction, there are many uncont...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21D11/10
CPCE21D11/10E21D11/102
Inventor 蒋忠全钟鹏段平安乔磊韩宇赵荣立蒋礼明杜发平孟树红王助锋董晓珂罗云森
Owner CHINA RAILWAY TUNNEL GROUP CO LTD