Construction Method for Installing High and Large Formwork in Super High-rise Elevator Shaft

A technology of tall formwork and elevator shaft, applied in basic structure engineering, construction and other directions, can solve the problems of complex construction process, long construction time, quality defects, etc., and achieve the effect of good promotion value, shortening construction period and saving construction period.

Active Publication Date: 2019-07-30
SHANGHAI BAOYE GRP CORP
View PDF4 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] Usually, for similar well pits that are relatively deep, in order to prevent the formwork system from being unstable against the side, screw rods are embedded on the steel skeleton for connection, and internal braces are used for reinforcement; in order to prevent the formwork from floating, usually on the formwork system Taking the form of stacking, such as stacking formwork and steel bar counterweight, the construction time is long and the construction process is complicated
[0006] Therefore, in order to solve the inconvenience and quality defects caused by the usual practice of elevator shaft formwork reinforcement system, it is already a problem worth studying to provide a new construction method for super high-rise elevator shaft high formwork reinforcement

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction Method for Installing High and Large Formwork in Super High-rise Elevator Shaft

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0040] Project overview: The comprehensive development project of Sanyang Road Wind Tower of an urban rail transit line 7 consists of a tower and a podium, with 3 floors underground, 46 floors above the tower, and 7 floors above the podium. The total construction area is 118461m 2 , of which the total construction area on the ground is 94295.8m 2 , the total underground construction area is 24165.2m 2 , the building height is 229.1m.

[0041] The thickness of the raft around the core tube in the tower area and at the bottom of the elevator shaft is 3.3m, and the thickness of the raft in the tower core area is 4m, 4.95m, 6m, 7m, 8m, 9m, and 10m in total; the elevation of the raft in the tower area is -16.3m, the deepest bottom elevation is -26.3m. There are 14 elevations in the tower area (including elevator shafts and sump pits).

[0042] Dimensions of elevator shaft (length x width x height): 5600mm x 2500mm x 5700mm (high area elevator, 2 in 1, 4 in total),

[0043] 560...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses an installation and construction method of a high formwork of a super high-rise elevator shaft. The installation and construction method comprises two stages including a construction preparation stage and a construction operation procedure, wherein the construction operation procedure comprises the steps of (1) processing the formwork, (2) installing and fixing a bottom die, (3) installing an inner support frame, (4) installing and fixing a side die, (5) integrally reinforcing, (6) hoisting a box body in place, (7) installing a connecting reinforcement, (8) pouring concrete, and monitoring, and (9) removing the formwork. According to the reinforcement and construction method of the high formwork of the super high-rise elevator shaft, traditional formworks, battens and steel pipes are used as raw materials, the formworks are used as face plates, the battens are used as inner ridges, the steel pipes are used as outer ridges so as to manufacture the box body, a lifting machine is installed in the elevator shaft, steel pipe supports are arranged in the box body so as to solve the problem of side pressure of concrete to the box body, the box body is locked by adopting the steel pipes so as to solve the problem of floating resistance of the box body to the concrete, and the steel pipes are connected with bottom reinforcements of a raft by utilizing round steel.

Description

technical field [0001] The invention is designed in the field of building construction, in particular to a construction method suitable for the installation of well pit templates in elevator shafts, sump pits, large venues and industrial plant equipment foundations in super high-rise rafts. Background technique [0002] With the development of society, especially the accelerating process of urbanization, the large flow of population has led to a large number of people in some cities where social resources are relatively concentrated, making it necessary to accommodate more people and other people outside the limited land area. Social resources have made land very tense. Therefore, the development of high-rise buildings and underground buildings has become the solution to the maximum utilization rate of limited land. [0003] With the development of super high-rise building technology, the building height has been refreshed by new records again and again. In order to make fu...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): E02D19/22E02D27/01E02D27/44
CPCE02D19/22E02D27/013E02D27/44E02D2250/0007E02D2250/0023
Inventor 沈育龙杨统元丁恩亮王杰闫富华
Owner SHANGHAI BAOYE GRP CORP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products