Construction method for double-steel-plate shear wall in continuous casting main machine area in limited space
A technology of limited space and construction method, applied in building maintenance, construction, building structure, etc., can solve problems such as many hidden dangers, narrow space in the continuous casting host area, and difficulty in installing steel plates, so as to improve construction efficiency. And the effect of construction quality and construction efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0022] The present invention is further illustrated below by specific examples.
[0023] A construction method for double-steel plate shear walls in the main continuous casting area in a confined space, including
[0024] Step 1. Construction preparation;
[0025] Step 2, planting bars on the equipment foundation;
[0026] Step 3. Install the first section of inner "L"-shaped steel plate;
[0027] Step 4, steel bar binding;
[0028] Step 5. Install the first section of outer "L"-shaped steel plate;
[0029] Step 6, concrete pouring and maintenance;
[0030] Step 7 Repeat steps 3 to 6 to carry out the construction of the double steel plate shear wall in other sections until it is completed;
[0031] in,
[0032] Construction preparation in step 1 includes steel plate lofting, processing, stud welding, measurement and setting out;
[0033] In step 3, according to the space and the lifting capacity of the hoisting machinery, the steel plate is processed into "L" shapes in ...