A construction dust removal device
A dust removal device and construction technology, applied in the separation method, the use of liquid separation agent, the separation of dispersed particles, etc., can solve the problems of small dust particle size, increased dust removal cost, wide diffusion surface, etc., to avoid waste of water resources, Reduce the cost of dust removal and increase the effect of dust removal area
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
no. 1 approach
[0026] First implementation: see Figure 1-6, an embodiment provided by the present invention: a dust removal device for building construction, including an air duct 1, an air supply duct 2, a box body 3, a first servo motor 4 and a rotating frame 5, and the two sides of the box body 3 are installed by bearings Walking wheel 302 is arranged, and walking wheel 302 can move conveniently when promoting device, thereby can use everywhere in the middle of building construction, and one side of walking wheel 302 is fixedly equipped with universal wheel 304, and universal wheel 304 makes its device move , guide the device to turn, the side of the box body 3 is provided with four groups of water level observation holes 301, and the interior of the water level observation holes 301 is provided with a transparent glass plate, so that the water level in the middle of the water tank can be observed, thereby facilitating the regular addition of water to the device, the water level observati...
no. 2 approach
[0037] The second embodiment: a dust removal device for building construction, including an air duct 1, an air supply duct 2, a box body 3, a first servo motor 4 and a rotating frame 5, and traveling wheels are installed on both sides of the box body 3 through bearings 302, a universal wheel 304 is fixedly installed on one side of the walking wheel 302, four sets of water level observation holes 301 are installed on the side of the box body 3, and two sets of solar cells are fixedly installed on one side of the water level observation hole 301 plate 303, the inside of the box body 3 is provided with a water tank 9, one side of the water tank 9 is connected to the water pump 10 through the water inlet 1001, the bottom of the water pump 10 is equipped with a mounting seat 1003, and the top of the water pump 10 The water delivery port 1002 is fixedly installed, and the water delivery port 1002 is located on the symmetrical center line of the projected area of the air pipe 1 and ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com