Three-wall integrated underground continuous wall construction method

A technology of underground diaphragm wall and construction method, applied in sheet pile wall, foundation structure engineering, construction, etc., can solve the problems of cumbersome construction, engineering troubles, large resource consumption, etc.

Active Publication Date: 2019-10-08
湖南三科土木特种工程施工有限公司
View PDF6 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] Aiming at the deficiencies of the prior art, the present invention provides a three-in-one underground continuous wall construction method, which solves the problem that the existing underground continuous wall needs to select materials according to different functions, and at the same time, additional construction is required for different functional walls. , occupies a wide area, consumes a lot of resources, and at the same time, the construction is more cumbersome, which brings many troublesome problems to the project

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Three-wall integrated underground continuous wall construction method
  • Three-wall integrated underground continuous wall construction method
  • Three-wall integrated underground continuous wall construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0030] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0031] see Figure 1-5 , the embodiment of the present invention provides a technical solution: a three-in-one underground continuous wall construction method, specifically comprising the following steps:

[0032] Step 1. Prepare for measurement: through calculation and on-site load test, determine the reasonable penetration depth of the load-bearing underground diaphragm wall, and then determine the prefabricated floor 1 and stable floor 2 according to the ac...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a three-wall integrated underground continuous wall construction method. The method comprises the steps that 1, preparation is made for measurement; 2, a bottom plate is assembled; 3, assembly walls are installed; 4, assemblies are installed, wherein a second stable frame at the bottoms of prefabricated connecting pieces manufactured in step 1 slides into pouring holes assembled in step 3, and meanwhile, first connecting cylinders at the bottoms of the prefabricated connecting pieces are clamped on the surfaces of second connecting cylinders; 5, a top plate is assembled; and 6, pouring and fixing are carried out. The invention relates to the technical field of civil engineering. According to the three-wall integrated underground continuous wall construction method,the prefabricated assemblies are used for assembly, the structure is simple, assembling saves more time, the construction speed is higher, and the efficiency is better; then a frame type formwork is assembled, concrete is used for pouring, and the structure is more stable so that the waterproof and soil blocking effects can be achieved, the weighing function can be achieved, the purpose of integrating the three walls is achieved, space and resources are saved, and the construction trouble is reduced.

Description

technical field [0001] The invention relates to the technical field of civil engineering, in particular to a three-wall-in-one underground continuous wall construction method. Background technique [0002] The underground diaphragm wall is a kind of trenching machine used on the ground in the remote foundation project. Along the peripheral axis of the deep excavation project, under the condition of mud retaining wall, a narrow and long deep groove is excavated. After cleaning the groove, hang it in the groove Put the reinforcement cage, and then use the conduit method to pour the underwater concrete to form a unit groove section, so that a continuous reinforced concrete wall is built underground, which can be used as a water interception, seepage prevention, load bearing, and water retaining structure. Construction of deep foundation pit support and reverse construction in dense building complexes can be used in various geological conditions, including construction in sandy ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E02D5/20
CPCE02D5/20
Inventor 王欢
Owner 湖南三科土木特种工程施工有限公司