Assembly type recoverable round working pit reserving door opening and construction method thereof
A technology of circular work and construction method, applied in excavation, artificial islands, water conservancy projects, etc., can solve the problems of difficult subsidence, long construction period and high cost, and achieve the effect of shortening construction period, reducing construction period and ensuring safety.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0047]A construction method for an assembled recyclable circular working pit with reserved door openings. First, the functional requirements design of the circular working well is completed, and then the construction of support piles, the installation of prefabricated crown beams, and the construction of edge protection are carried out sequentially. The earthwork excavation of the circular working well, the soil retaining panel, and the circular inner support beam are alternately constructed, and the door opening is reserved at the same time. Finally, the ladder for entering the circular working well and the bottom sealing of the circular working well are installed to complete the assembly of the reserved door opening. In the construction of a recyclable circular working well, after the work in the well is completed, the working well components such as the retaining panel, the annular inner support beam, the crown beam and the support pile are gradually recovered during the back...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 