Electric tower structure and construction method thereof
A technology of electrical towers and mounting plates, applied in the directions of towers, building components, building types, etc., can solve the problems of tower overturning, tower shaking, bolt loosening, etc., and achieve the effect of improving seismic performance and reducing vibration amplitude.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0042] Embodiment one: refer to figure 1 , an electric tower structure, including an electric tower body 1, a mounting foot 2 and a base 3 from top to bottom in sequence, and the base 3 is formed by pouring concrete. refer to figure 2 and image 3 The middle part of the base 3 is provided with a groove 4 with a square cross section, and the lower end of the mounting foot 2 is horizontally connected with a square mounting plate 5, and the mounting foot 2 and the mounting plate 5 are connected by high-strength bolts and nuts.
[0043] refer to image 3 and Figure 4, the bottom of the mounting plate 5 is horizontally provided with a square damping plate 6 slidingly connected to the bottom wall of the groove 4, the lower surface of the damping plate 6 fits with the bottom wall of the groove 4, and the damping plate 6 is provided with several Through the first bolt 7 of the shock absorbing plate 6 and the mounting plate 5, in this embodiment, each side of the shock absorbing ...
Embodiment 2
[0052] Embodiment two: a kind of construction method of electric tower structure, comprises the following steps:
[0053] Pouring the foundation 3: Excavate the foundation pit in the set area, install the formwork and place the tied steel cage, pre-embed the second spring 10 at the set position, pour concrete into the formwork, and form the foundation 3 after the maintenance is completed;
[0054] The installation of damping plate 6: Install the first bolt 7 on the damping plate 6, put the damping plate 6 into the bottom of the groove 4 of the foundation pit, and connect one end of the second spring 10 to the side wall of the damping plate 6 fixed connection;
[0055] Installation of the mounting plate 5: install the first spring 9 around the first bolt 7, place the mounting plate 5 above the shock absorbing plate 6, and fix the two ends of the first spring 9 to the mounting plate 5 and the shock absorbing plate 6 respectively Connect, make the first bolt 7 pass through the m...
Embodiment 3
[0057] Embodiment three: a construction method of an electric tower structure, comprising the following steps:
[0058] Pouring foundation 3: Excavate the foundation pit in the set area, install the formwork and put in the tied steel cage, pre-embed the second spring 10, guide rod 11 and second shock pad 15 at the set position, and insert them into the formwork Concrete is poured, and the base 3 is formed after the curing is completed;
[0059] The installation of damping plate 6: install the first bolt 7 and the third spring 13 on the damping plate 6, put the damping plate 6 into the bottom of the groove 4 of the foundation pit, and connect one end of the second spring 10 with the damping The side wall of the plate 6 is fixedly connected, and the guide rod 11 extends into the guide groove 12 of the damping plate 6;
[0060] Installation of the mounting plate 5: install the first spring 9 around the first bolt 7, place the mounting plate 5 above the shock absorbing plate 6, a...