A construction method and technology of steel structure, applied in the direction of building construction, building maintenance, construction, etc., can solve the problems of high cost, poor applicability, low efficiency, etc., and achieve the effect of strong applicability, convenient construction and simple operation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0040] figure 1 The construction equipment used for fixing and transporting steel structures is introduced. The construction equipment can remove steel structural beams or steel structural columns, usually structural steel beams or structural steel columns are I-beams or channel steels. Specifically, the construction equipment includes a walking device 1, a turning device 4 arranged above the traveling device 1, a mechanical arm 5 installed on the turning device 4, and a fixing device 6 in the present invention is arranged at the front end of the mechanical arm 5, and the walking The device 1 is located on the working surface 7, which can be a floor slab, and the fixing device 6 is used to remove the steel structure 8, figure 1 The medium steel structure 8 is an I-shaped steel beam, and of course the steel structure 8 can also be a steel structure column. The construction equipment may also include several legs 2, which may be connected to the frame of the traveling device 1 ...
Embodiment 2
[0049] This embodiment provides a construction method for dismantling a steel structure, using the construction equipment for fixing and transporting the steel structure in Embodiment 1 to dismantle the steel structure. Described construction method comprises the steps:
[0050] The construction equipment walks to the flat surface of the steel structure directly opposite, and adjusts the mechanical arm so that the fixing device is parallel to the steel structure and close to the surface of the steel structure;
[0051] Start the electromagnet, fix the steel structure to be removed firmly, and remove the steel structure;
[0052] Use the walking device of the construction equipment to transport the dismantled steel structure to the designated location, adjust the mechanical arm to make the steel structure park firmly, and turn off the electromagnet to separate the fixed structure from the steel structure. In order to complete the demolition and transportation of the steel stru...
Embodiment 3
[0059] Because obstacles are often encountered on construction sites, the construction equipment for fixing and transporting steel structures provided in this embodiment also has the function of overcoming obstacles, mainly by improving the walking device in the first embodiment. combine Figure 4 with Figure 5 As shown, the traveling device includes a chassis 11 and a traveling mechanism 12 arranged on both sides of the chassis 11 . Described running mechanism 12 comprises first roller 13, second roller 14, adjustment flywheel 15, crawler belt 16, first elevator wheel system 17 and second elevator wheel system 18; Described first roller 13, first elevator wheel system 17 , the second lifting wheel system 18, and the second roller 14 are arranged on the chassis 11 in sequence; Turn and brake. combine Figure 5 with Image 6 As shown, the first lifting wheel system 17 and the second lifting wheel system 18 both include a box body 171, a lifting device 172 arranged on the ...