Production equipment and production method of pipeline transported coal slurry
A technology for production equipment and coal slurry, which is applied in the field of production equipment for coal slurry transportation by pipeline, can solve the problems of high return rate, high transportation cost, and large environmental pollution, so as to ensure safety and stability, and solve large-scale long-term problems. The effect of distance transport
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0047]A kind of production method of pipeline transportation coal slurry, specifically implement according to the following steps:
[0048] Step 1: Rod Mill 4 Grinding Pulping:
[0049] In the future, the coal raw material will be crushed by the fine crusher 1 to less than 6 mm and then dropped to the powder coal buffer bin 2, then quantitatively fed to the rod mill 4 by the quantitative feeder 3, and at the same time, water will be added to the rod mill 4 through the water inlet 24 of the first process. The electromagnetic flowmeter controls the amount of water added, and then fully grinds the coal slurry through the rod mill 4 and transports it to the safety screen 5 through the drum screen with a screen hole size of 3 mm on the rod mill 4; the oversize of the drum screen passes through the slag outlet Pull away with dolly 14;
[0050] In step 1, the incoming coal raw material is bituminous medium long-flame coal.
[0051] In step 1, the feeding amount of the quantitative ...
Embodiment 2
[0059] A kind of production method of pipeline transportation coal slurry, specifically implement according to the following steps:
[0060] Step 1: Rod Mill 4 Grinding Pulping:
[0061] In the future, the coal raw material will be crushed by the fine crusher 1 to less than 6 mm and then dropped to the powder coal buffer bin 2, then quantitatively fed to the rod mill 4 by the quantitative feeder 3, and at the same time, water will be added to the rod mill 4 through the water inlet 24 of the first process. The electromagnetic flowmeter controls the amount of water added, and then fully grinds the coal slurry through the rod mill 4 and transports it to the safety screen 5 through the drum screen with a screen hole size of 3 mm on the rod mill 4; the oversize of the drum screen passes through the slag outlet Pull away with dolly 14;
[0062] In step 1, the incoming coal raw material is non-caking coal.
[0063] In step 1, the feeding amount of the quantitative feeder 3 is 150t / ...
Embodiment 3
[0071] A kind of production method of pipeline transportation coal slurry, specifically implement according to the following steps:
[0072] Step 1: Rod Mill 4 Grinding Pulping:
[0073] In the future, the coal raw material will be crushed by the fine crusher 1 to less than 6 mm and then dropped to the powder coal buffer bin 2, then quantitatively fed to the rod mill 4 by the quantitative feeder 3, and at the same time, water will be added to the rod mill 4 through the water inlet 24 of the first process. The electromagnetic flowmeter controls the amount of water added, and then fully grinds the coal slurry through the rod mill 4 and transports it to the safety screen 5 through the drum screen with a screen hole size of 3 mm on the rod mill 4; the oversize of the drum screen passes through the slag outlet Pull away with dolly 14;
[0074] In step 1, the incoming coal raw material is non-caking coal.
[0075] In step 1, the feeding amount of the quantitative feeder 3 is 200t / ...