Continuous casting funnel-shaped crystallizer molten steel solidification and casting blank simulation device and using method thereof
A technology for simulating device and crystallizer, applied in the field of iron and steel metallurgy
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0069] The equipment used in this example is figure 1 shown.
[0070] In this embodiment, the steps of the continuous casting funnel mold molten steel solidification and slab simulation method are as follows:
[0071] 1) Put a 50Kg experimental steel block with a size of 50×50×50mm into the induction steelmaking furnace, and in the case of argon protection, start the induction heating to heat the molten steel to 1500°C and keep it for 20 minutes until it is completely melted into steel liquid.
[0072] 2) Add 100g of mold slag particles to the surface of the molten steel. The high-temperature molten steel will melt the mold slag particles into a liquid state and cover the surface of the molten steel to absorb the floating inclusions on the surface of the molten steel. After 5 minutes, the surface of the molten steel will absorb the inclusions. Remove the protection residue.
[0073] 3) Add 200g of mold slag particles to the molten steel again, and after standing for 10 min...